DMS | PreProd | Resend Emails are not receiving for PDF and HTML File ype

    Details

    • Type: Bug
    • Status: Done
    • Priority: Medium
    • Resolution: Done
    • Affects Version/s: None
    • Fix Version/s: CBAT Offer Letter - Fall
    • Labels:
      None

      Description

      Environment: PreProd
      Page: Completed Sent Forms Libraray

      Issue: Resend Emails are not receiving for PDF and HTML File Type

       

      Sachin Hingole

        Attachments

          Activity

          mohd.belal Mohd Belal (Inactive) logged work - 02/Jun/19 11:38 PM - edited
          • Time Spent:
            8h
             
            <No comment>
          priya.dhamande Priya Dhamande (Inactive) created issue -
          shashikant.mishra ShashiKant Mishra (Inactive) made changes -
          Field Original Value New Value
          Fix Version/s CBAT Offer Letter - Fall [ 10607 ]
          mohd.belal Mohd Belal (Inactive) made changes -
          Assignee Samir [ samir ] Mohd Belal [ mohd.belal ]
          mohd.belal Mohd Belal (Inactive) made changes -
          Sprint DMS - Fall Sprint 5 [ 164 ]
          Remaining Estimate 8h [ 28800 ]
          Original Estimate 8h [ 28800 ]
          mohd.belal Mohd Belal (Inactive) made changes -
          Status To Do [ 10000 ] In Progress [ 3 ]
          mohd.belal Mohd Belal (Inactive) logged work - 12/Jun/19 02:14 AM
          • Time Spent:
            4h
             

            Checked the case

          Hide
          mohd.belal Mohd Belal (Inactive) added a comment -

          Hi Priya Dhamande,

          Checked and verified the above, getting emails for PDF and HTML on click of Resend button from Completed form Library.

          cc - Samir

          Thanks

          Show
          mohd.belal Mohd Belal (Inactive) added a comment - Hi Priya Dhamande , Checked and verified the above, getting emails for PDF and HTML on click of Resend button from Completed form Library. cc - Samir Thanks
          mohd.belal Mohd Belal (Inactive) made changes -
          Remaining Estimate 8h [ 28800 ] 4h [ 14400 ]
          Time Spent 4h [ 14400 ]
          Worklog Id 182745 [ 182745 ]
          mohd.belal Mohd Belal (Inactive) made changes -
          Status In Progress [ 3 ] In QA Testing [ 11901 ]
          mohd.belal Mohd Belal (Inactive) made changes -
          Assignee Mohd Belal [ mohd.belal ] Priya Dhamande [ priya.dhamande ]
          mohd.belal Mohd Belal (Inactive) logged work - 16/Jun/19 11:38 PM
          • Time Spent:
            8h
             
            <No comment>
          mohd.belal Mohd Belal (Inactive) logged work - 17/Jun/19 11:37 PM
          • Time Spent:
            10h
             
            <No comment>
          priya.dhamande Priya Dhamande (Inactive) made changes -
          Attachment Screenshot (2529).png [ 110661 ]
          Hide
          priya.dhamande Priya Dhamande (Inactive) added a comment -

          Environment: Preprod
          Login: End User

          The issue of PDF and HTML mails not receiving is resolved and verified. Able to receive emails as expected.

          Screen capture attached for reference. So, making jira done.

          Sachin Hingole Rohan J Khandave Samir

          Show
          priya.dhamande Priya Dhamande (Inactive) added a comment - Environment: Preprod Login: End User The issue of PDF and HTML mails not receiving is resolved and verified. Able to receive emails as expected. Screen capture attached for reference. So, making jira done. Sachin Hingole Rohan J Khandave Samir
          priya.dhamande Priya Dhamande (Inactive) made changes -
          Resolution Done [ 10000 ]
          Status In QA Testing [ 11901 ] Done [ 10001 ]
          priya.dhamande Priya Dhamande (Inactive) made changes -
          Assignee Priya Dhamande [ priya.dhamande ] Mohd Belal [ mohd.belal ]
          samir Samir made changes -
          Epic Link DMS-473 [ 75966 ]
          priya.dhamande Priya Dhamande (Inactive) logged work - 18/Jun/19 04:28 AM - edited
          • Time Spent:
            0.5h
             

            preprod testng

          priya.dhamande Priya Dhamande (Inactive) made changes -
          Remaining Estimate 4h [ 14400 ] 0h [ 0 ]
          Time Spent 4h [ 14400 ] 34h [ 122400 ]
          Worklog Id 184821 [ 184821 ]
          priya.dhamande Priya Dhamande (Inactive) made changes -
          Remaining Estimate 0h [ 0 ] 29.5h [ 106200 ]
          Time Spent 34h [ 122400 ] 4.5h [ 16200 ]
          Worklog Id 184821 [ 184821 ]
          mohd.belal Mohd Belal (Inactive) made changes -
          Remaining Estimate 29.5h [ 106200 ] 19.5h [ 70200 ]
          Time Spent 4.5h [ 16200 ] 14.5h [ 52200 ]
          Worklog Id 205441 [ 205441 ]
          mohd.belal Mohd Belal (Inactive) made changes -
          Remaining Estimate 19.5h [ 70200 ] 11.5h [ 41400 ]
          Time Spent 14.5h [ 52200 ] 22.5h [ 81000 ]
          Worklog Id 205442 [ 205442 ]
          mohd.belal Mohd Belal (Inactive) made changes -
          Remaining Estimate 11.5h [ 41400 ] 3.5h [ 12600 ]
          Time Spent 22.5h [ 81000 ] 30.5h [ 109800 ]
          Worklog Id 205443 [ 205443 ]
          mohd.belal Mohd Belal (Inactive) made changes -
          Worklog Id 205443 [ 205443 ]
          Transition Time In Source Status Execution Times
          Mohd Belal (Inactive) made transition -
          To Do In Progress
          5d 18h 52m 1
          Mohd Belal (Inactive) made transition -
          In Progress In QA Testing
          1h 32m 1
          Priya Dhamande (Inactive) made transition -
          In QA Testing Done
          5d 23h 18m 1

            People

            Assignee:
            mohd.belal Mohd Belal (Inactive)
            Reporter:
            priya.dhamande Priya Dhamande (Inactive)
            Votes:
            0 Vote for this issue
            Watchers:
            2 Start watching this issue

              Dates

              Created:
              Updated:
              Resolved:

                Time Tracking

                Estimated:
                Original Estimate - 8h Original Estimate - 8h
                8h
                Remaining:
                Time Spent - 30.5h Remaining Estimate - 3.5h
                3.5h
                Logged:
                Time Spent - 30.5h Remaining Estimate - 3.5h
                30.5h