      Description

      Update to new schema

      Script for data migration

        Attachments

          Activity

          harshveer.singh Harshveer Singh (Inactive) created issue -
          harshveer.singh Harshveer Singh (Inactive) made changes -
          Field Original Value New Value
          Remaining Estimate 10h [ 36000 ] 16h [ 57600 ]
          Original Estimate 10h [ 36000 ] 16h [ 57600 ]
          harshveer.singh Harshveer Singh (Inactive) made changes -
          Status To Do [ 10000 ] In Progress [ 3 ]
          harshveer.singh Harshveer Singh (Inactive) logged work - 31/Oct/19 11:30 AM
          • Time Spent:
            8h
             
            <No comment>
          narendra.kumar Narendra Kumar made changes -
          Fix Version/s Winter 2020 CBAT Integration [ 11316 ]
          harshveer.singh Harshveer Singh (Inactive) made changes -
          Remaining Estimate 16h [ 57600 ] 8h [ 28800 ]
          Time Spent 8h [ 28800 ]
          Worklog Id 211749 [ 211749 ]
          harshveer.singh Harshveer Singh (Inactive) logged work - 01/Dec/19 10:30 AM
          • Time Spent:
            8h
             
            <No comment>
          harshveer.singh Harshveer Singh (Inactive) logged work - 02/Dec/19 10:30 AM
          • Time Spent:
            8h
             
            <No comment>
          Hide
          Ganesh.sadawarte Ganesh Sadawarte (Inactive) added a comment -

          Hi All, 

          Please find below task details.

          • Code compilation : Code changes are not properly complied.
          • Database changes.
          • Verify send forms.
          • Verify create document.
          • Verify user creation for one company...

          Note: As we checked found that there would be no logic added to add person against multiple company so that need to be add.

          CC-Samir,Rohan J Khandave

          Thanks,

          Ganesh

          Show
          Ganesh.sadawarte Ganesh Sadawarte (Inactive) added a comment - Hi All,  Please find below task details. Code compilation : Code changes are not properly complied. Database changes. Verify send forms. Verify create document. Verify user creation for one company... Note : As we checked found that there would be no logic added to add person against multiple company so that need to be add. CC- Samir , Rohan J Khandave Thanks, Ganesh
          Ganesh.sadawarte Ganesh Sadawarte (Inactive) made changes -
          Remaining Estimate 8h [ 28800 ] 0h [ 0 ]
          Time Spent 8h [ 28800 ] 16h 10m [ 58200 ]
          Worklog Id 215525 [ 215525 ]
          Ganesh.sadawarte Ganesh Sadawarte (Inactive) made changes -
          Assignee Harshveer Singh [ harshveer.singh ] Ganesh Sadawarte [ ganesh.sadawarte ]
          Ganesh.sadawarte Ganesh Sadawarte (Inactive) logged work - 04/Dec/19 05:34 PM
          • Time Spent:
            8h 10m
             
            <No comment>
          Hide
          Ganesh.sadawarte Ganesh Sadawarte (Inactive) added a comment -

          Hi,

          As per discussion with Samir putting this on hold. As we found only database level changes.

          Thanks,

          Ganesh

          Show
          Ganesh.sadawarte Ganesh Sadawarte (Inactive) added a comment - Hi, As per discussion with Samir  putting this on hold. As we found only database level changes. Thanks, Ganesh
          Ganesh.sadawarte Ganesh Sadawarte (Inactive) made changes -
          Status In Progress [ 3 ] On Hold [ 10507 ]
          Ganesh.sadawarte Ganesh Sadawarte (Inactive) made changes -
          Assignee Ganesh Sadawarte [ ganesh.sadawarte ] Harshveer Singh [ harshveer.singh ]
          harshveer.singh Harshveer Singh (Inactive) made changes -
          Time Spent 16h 10m [ 58200 ] 24h 10m [ 87000 ]
          Worklog Id 219945 [ 219945 ]
          harshveer.singh Harshveer Singh (Inactive) made changes -
          Time Spent 24h 10m [ 87000 ] 32h 10m [ 115800 ]
          Worklog Id 219946 [ 219946 ]
          narendra.kumar Narendra Kumar made changes -
          Resolution Done [ 10000 ]
          Status On Hold [ 10507 ] Done [ 10001 ]
          Transition Time In Source Status Execution Times
          Harshveer Singh (Inactive) made transition -
          To Do In Progress
          5d 23h 1
          Ganesh Sadawarte (Inactive) made transition -
          In Progress On Hold
          35d 3h 58m 1
          Narendra Kumar made transition -
          On Hold Done
          35d 1h 35m 1

            People

            Assignee:
            harshveer.singh Harshveer Singh (Inactive)
            Reporter:
            harshveer.singh Harshveer Singh (Inactive)
            Votes:
            0 Vote for this issue
            Watchers:
            1 Start watching this issue

              Dates

              Created:
              Updated:
              Resolved:

                Time Tracking

                Estimated:
                Original Estimate - 16h Original Estimate - 16h
                16h
                Remaining:
                Remaining Estimate - 0h
                0h
                Logged:
                Time Spent - 32h 10m
                32h 10m