Type:
Enhancement
-
Status: Closed
-
Priority:
High
-
Resolution: Unresolved
-
Affects Version/s: None
-
Fix Version/s: None
-
Component/s: I9 Stand Alone
-
Labels:None
-
Module:I9 Stand Alone
-
Reported by:Client
-
Company:MATT
-
Item State:Production Complete - Closed
-
Issue Importance:Q1
-
Sprint:NF Sprint 2
-
- Time Spent:
- 1h
-
Revising E-verify tutorial
-
- Time Spent:
- 3h
-
Initial Submission for Case 3 and Analysis for Download and Upload Letters
-
- Time Spent:
- 2h
-
Saving Eligibility statements in DB
Downloading Letters to our system
-
- Time Spent:
- 3h
-
SatusAnaysis and UI design for TnCprocess and opening Popup from I9 Status
-
- Time Spent:
- 2.5h
-
Completed UI for TNC Process
Discussion with Swapnil regarding TNC Process
-
- Time Spent:
- 3h
-
Submitting Case 8 from self test cases.
-
- Time Spent:
- 7h
-
Uploading FAN letters to File Server retrieved from E-Verify.
Creating Models and Actions for TNC Process popup.
Working TNCProcess UI.
Implementation of Download Letters (FAN) from popup (inprogress)
-
- Time Spent:
- 4h
-
Working for I9 Uploading and Downloading Letters and Popup
-
- Time Spent:
- 1h
-
I9 Verifiaction KT to Yogesh
-
- Time Spent:
- 3h
-
Analysis for Adding OnBoard Tour forms menu in Additional Forms list
-
- Time Spent:
- 4h
-
Implementation of Additional Forms for Tour Builder:
Analysis and Discussion with Swapnil and Creating function at Business logic
-
- Time Spent:
- 2h
-
Checking and Implementing of Additional Forms at Tour Builder for EDS save and Tour Steps save.
-
- Time Spent:
- 2h
-
Adding all Tour Builder forms to Additional Forms menu at LONG on main and HSPL company.
Testing impacted changes on main and HSPL
-
- Time Spent:
- 3h
-
Updating Employee approval statuses
-
- Time Spent:
- 0.5h
-
Discussion with Hrishikesh and email communication for I9 everify statuses.
-
- Time Spent:
- 2h
-
Close case validations and Employee status updation
-
- Time Spent:
- 3h
-
Refer case, Close Case & TNCNotified implementation in MVC pages.
Submitting one case to check implemenattion
-
- Time Spent:
- 1.2h
-
Code review , Discussion with Niteen , TNC process checks
-
- Time Spent:
- 4h
-
TNC Process popup check for before and after referral
Update ApprovalReturnStatus or Message Code to DB after referral process.
Business login change for TNC process
-
- Time Spent:
- 2.5h
-
Working on TNC process and working on download RDC and FAN notice
-
- Time Spent:
- 2h
-
Validation for Message Code 43 and Empty Message Code handling at I9ApprovalStatus.
Unit Testing for above changes
-
- Time Spent:
- 2.5h
-
Street1 and Stree2 address merged in I9 form
Completing checklist
-
- Time Spent:
- 6h
-
Completing remaining checklist for I9 forms.
Removing unnecessary code from model.
Completing remaining I9 Validations.
Writing scripts to Add/Remove data from/to DB
-
- Time Spent:
- 5.5h
-
Case 3 - Resubmiting password case to check Refer Case, Close case, Upload/Download Letters and TNC process. Unit Testing on Upload/Download letters.
-
- Time Spent:
- 3.2h
-
Email communication for I9 and discussion
-
- Time Spent:
- 5h
-
Late Hire Over Due Date of I9 implementation, Validation, UI and Submission to E-verify
-
- Time Spent:
- 3h
-
I9 Overdue date Unit Testing and Case 3 Submission to E-verify
-
- Time Spent:
- 0.75h
-
Production certification email communication
-
- Time Spent:
- 2.75h
-
Close Case and Action icon changes for better UX
-
- Time Spent:
- 4h
-
Completion of Passport case (Case 3) with different scenarios (DB Save, Validation, Model changes).
Worked on Get resolved cases. (Model and UI Changes).
-
- Time Spent:
- 3h
-
Analysed files to check-in on Stage.
Check-in for All I9 Views, Model and Controllers (With Comparing).
-
- Time Spent:
- 4h
-
Check-ins for Value Object, Business Logic and Localization Files
-
- Time Spent:
- 1h
-
Other tech discussion and Collecting DB scripts to check-in.
-
- Time Spent:
- 1.5h
-
Discussion with Niteen, Shyam, Samir
-
- Time Spent:
- 1.8h
-
Checking MOU and analysis on MOU
-
- Time Spent:
- 0.5h
-
Technical discussion with Mahendra and Rajendra
-
- Time Spent:
- 3h
-
Executing Production certification test cases
-
- Time Spent:
- 4h
-
E-verify production certification test cases completion and email communication