Type:
Enhancement
-
Status: Resolution Setting
-
Priority:
High
-
Resolution: Done
-
Component/s: BenAdmin
-
Labels:
-
Module:BenAdmin - Enrollment
-
Reported by:Client
-
Item State:LB QA - On Hold
-
Issue Importance:Good To Have
-
Sprint:WT Sprint 37 - Enhancement
-
Severity:Simple
Field | Original Value | New Value |
---|---|---|
Summary | Use Term as never effective logic if terming due to add'l eligibility criteria | Ability to remove termination date on an employee's record |
Dev Estimates | 40 |
Issue Importance | Good To Have [ 11802 ] | |
Item State | Parent values: Development(10200)Level 1 values: Development Backlog(10205) |
Priority | Medium [ 3 ] | High [ 2 ] |
Assignee | Satya [ ID10004 ] | Vaishali Poojari [ vaishali.poojari ] |
Developer | Vaishali Poojari [ vaishali.poojari ] |
Dev Due Date | 07/Aug/2017 |
-
- Time Spent:
- 1h
-
-Task discussion
-Started Analysis
Remaining Estimate | 24h [ 86400 ] | |
Original Estimate | 24h [ 86400 ] |
Remaining Estimate | 24h [ 86400 ] | 23h [ 82800 ] |
Time Spent | 1h [ 3600 ] | |
Worklog Id | 68318 [ 68318 ] |
Item State | Parent values: Development(10200)Level 1 values: Development Backlog(10205) | Parent values: Development(10200)Level 1 values: In Progress(10206) |
Status | New Request [ 10029 ] | Pending for Approval [ 10002 ] |
Status | Pending for Approval [ 10002 ] | Approved for Development [ 10003 ] |
Status | Approved for Development [ 10003 ] | In Development [ 10007 ] |
-
- Time Spent:
- 8h
-
-Discussion with Amruta.
-Analysis & Code debug.
-coding & Unit Testing.
Remaining Estimate | 23h [ 82800 ] | 15h [ 54000 ] |
Time Spent | 1h [ 3600 ] | 9h [ 32400 ] |
Worklog Id | 68951 [ 68951 ] |
Original Estimate | 24h [ 86400 ] | 40h [ 144000 ] |
-
- Time Spent:
- 8h
-
-Coding.
-Scenarios discussion & Unit Testing.
Worklog Id | 68951 [ 68951 ] |
-
- Time Spent:
- 6h
-
-Coding & Scenario Testing
Remaining Estimate | 15h [ 54000 ] | 7h [ 25200 ] |
Time Spent | 9h [ 32400 ] | 17h [ 61200 ] |
Worklog Id | 69346 [ 69346 ] |
Item State | Parent values: Development(10200)Level 1 values: In Progress(10206) | Parent values: Development(10200)Level 1 values: On Hold(10207) |
Remaining Estimate | 7h [ 25200 ] | 1h [ 3600 ] |
Time Spent | 17h [ 61200 ] | 23h [ 82800 ] |
Worklog Id | 69421 [ 69421 ] |
Remaining Estimate | 1h [ 3600 ] | 0h [ 0 ] |
Time Spent | 23h [ 82800 ] | 24.5h [ 88200 ] |
Worklog Id | 69484 [ 69484 ] |
Item State | Parent values: Development(10200)Level 1 values: On Hold(10207) | Parent values: Development(10200)Level 1 values: In Analysis(10204) |
Dev Due Date | 07/Aug/2017 | 07/Aug/2017 |
Sprint | WT Sprint 37 - Enhancement [ 86 ] |
-
- Time Spent:
- 4h
-
Discussion with umesh regarding enhancement.
Requirement gathering and scenarios.
Analysis of the enhancement.
Estimation
drafting documents
Analysis of how current system is working.
Assignee | Vaishali Poojari [ vaishali.poojari ] | Abhilash Warkari [ abhilash.warkari ] |
Developer | Vaishali Poojari [ vaishali.poojari ] | Abhilash Warkari [ abhilash.warkari ] |
-
- Time Spent:
- 8h
-
Analysis of the enhancement
Analysis of existing system working.
Existing code debugging.
Item State | Parent values: Development(10200)Level 1 values: In Analysis(10204) | Parent values: Development(10200)Level 1 values: In Progress(10206) |
Dev Due Date | 07/Aug/2017 | 11/Aug/2017 |
Dev Due Date | 11/Aug/2017 | 22/Aug/2017 |
Dev Due Date | 22/Aug/2017 | 19/Sep/2017 |
-
- Time Spent:
- 2h
-
Discussion with Abhilash
Code debugging for existing scenarios flow
-
- Time Spent:
- 8h
-
Discussion With umesh regarding scenarios and coding
Attachment | ST_315_Enhancement_Implementation.doc [ 61511 ] | |
Attachment | ST-315_Estimates.xls [ 61512 ] |
Dev Estimates | 40 | 46 |
Attachment |
|
Attachment | ST-315_Estimates.xls [ 61513 ] |
-
- Time Spent:
- 2h
-
Discussion with Abhilash and Amruta
Code debugging for existing scenarios flow
-
- Time Spent:
- 8h
-
Discussion With umesh
Coding and testing
Time Spent | 24.5h [ 88200 ] | 26.5h [ 95400 ] |
Worklog Id | 78843 [ 78843 ] |
Time Spent | 26.5h [ 95400 ] | 28.5h [ 102600 ] |
Worklog Id | 78844 [ 78844 ] |
Time Spent | 28.5h [ 102600 ] | 36.5h [ 131400 ] |
Worklog Id | 78919 [ 78919 ] |
Time Spent | 36.5h [ 131400 ] | 44.5h [ 160200 ] |
Worklog Id | 78921 [ 78921 ] |
Time Spent | 44.5h [ 160200 ] | 52.5h [ 189000 ] |
Worklog Id | 78924 [ 78924 ] |
Time Spent | 52.5h [ 189000 ] | 56.5h [ 203400 ] |
Worklog Id | 78929 [ 78929 ] |
-
- Time Spent:
- 3h
-
code review
unit testing
scenario discussion
-
- Time Spent:
- 8h
-
Coding
Review by umesh.
Testing various scenarios.
Item State | Parent values: Development(10200)Level 1 values: In Progress(10206) | Parent values: Development(10200)Level 1 values: Ready for Review(10208) |
QA | Priya Dhamande [ priya.dhamande ] |
Time Spent | 56.5h [ 203400 ] | 57h [ 205200 ] |
Worklog Id | 79158 [ 79158 ] |
Time Spent | 57h [ 205200 ] | 57.5h [ 207000 ] |
Worklog Id | 79159 [ 79159 ] |
Time Spent | 57.5h [ 207000 ] | 58h [ 208800 ] |
Worklog Id | 79160 [ 79160 ] |
Time Spent | 58h [ 208800 ] | 59h [ 212400 ] |
Worklog Id | 79161 [ 79161 ] |
Time Spent | 59h [ 212400 ] | 62h [ 223200 ] |
Worklog Id | 79162 [ 79162 ] |
Remaining Estimate | 0h [ 0 ] | 1h [ 3600 ] |
Time Spent | 62h [ 223200 ] | 61h [ 219600 ] |
Worklog Id | 79161 [ 79161 ] | |
Worklog Time Spent | 1h [ 3600 ] |
Worklog Id | 78844 [ 78844 ] |
Remaining Estimate | 1h [ 3600 ] | 1.5h [ 5400 ] |
Time Spent | 61h [ 219600 ] | 60.5h [ 217800 ] |
Worklog Id | 79159 [ 79159 ] | |
Worklog Time Spent | 0.5h [ 1800 ] |
-
- Time Spent:
- 8h
-
Review by amruta.
Analysis of the change suggested.
Testing various scenarios.
Attachment | TestCases_315.xls [ 61916 ] |
-
- Time Spent:
- 8h
-
Changed the validation message .
Added popup messages for validation as suggested by amruta.
Coding and testing for validations.
Dev Due Date | 19/Sep/2017 | 20/Sep/2017 |
Remaining Estimate | 1.5h [ 5400 ] | 0.5h [ 1800 ] |
Time Spent | 60.5h [ 217800 ] | 61.5h [ 221400 ] |
Worklog Id | 79914 [ 79914 ] |
Dev Due Date | 20/Sep/2017 | 21/Sep/2017 |
-
- Time Spent:
- 8h
-
Changed the whole flow of the code as requirements has changed.
Implemented new methods.
Made changes in the structure of the message which was return from the business logic.
And related code change was made in the view also to display appropriate message.
-
- Time Spent:
- 8h
-
Coding for some specific scenarios with umesh.
Added Conditions to handle overlap termination date.
Testing whole code
Discussion with umesh
Dev Due Date | 21/Sep/2017 | 22/Sep/2017 |
Dev Due Date | 22/Sep/2017 | 25/Sep/2017 |
-
- Time Spent:
- 8h
-
Testing Whole component.
Applied various scenarios.
Impact testing.
Tested functionality for new feature.
Discussion with umesh.
Code Review Date | 25/Sep/2017 | |
Code Reviewed By | Umesh Kadam [ 15302 ] |
Attachment | ST-315_Code_Review_Checklist .doc [ 62580 ] | |
Attachment | ST-315_Affected_Files.txt [ 62581 ] |
Item State | Parent values: Development(10200)Level 1 values: Ready for Review(10208) | Parent values: Development(10200)Level 1 values: Ready for Local Testing(10209) |
-
- Time Spent:
- 4h
-
Review of code
Code commit in trunk
Code Commit in LB
Testing.
Remaining Estimate | 0.5h [ 1800 ] | 0h [ 0 ] |
Time Spent | 61.5h [ 221400 ] | 65.5h [ 235800 ] |
Worklog Id | 81252 [ 81252 ] |
Time Spent | 65.5h [ 235800 ] | 73.5h [ 264600 ] |
Worklog Id | 81254 [ 81254 ] |
Time Spent | 73.5h [ 264600 ] | 81.5h [ 293400 ] |
Worklog Id | 81255 [ 81255 ] |
Time Spent | 81.5h [ 293400 ] | 89.5h [ 322200 ] |
Worklog Id | 81256 [ 81256 ] |
Production Due Date | 12/Oct/2017 | |
Stage Due Date | 5/Oct/17 [ 2017-10-05 ] |
Time Spent | 89.5h [ 322200 ] | 97.5h [ 351000 ] |
Worklog Id | 81257 [ 81257 ] |
Time Spent | 97.5h [ 351000 ] | 105.5h [ 379800 ] |
Worklog Id | 81258 [ 81258 ] |
Time Spent | 105.5h [ 379800 ] | 113.5h [ 408600 ] |
Worklog Id | 81262 [ 81262 ] |
Item State | Parent values: Development(10200)Level 1 values: Ready for Local Testing(10209) | Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) |
Assignee | Abhilash Warkari [ abhilash.warkari ] | Prasad Pise [ prasadp ] |
Assignee | Prasad Pise [ prasadp ] | Priya Dhamande [ priya.dhamande ] |
Item State | Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) | Parent values: LB QA(10201)Level 1 values: In Testing(10210) |
Status | In Development [ 10007 ] | Local Testing [ 10200 ] |
Stage Due Date | 5/Oct/17 [ 2017-10-05 ] | 9/Oct/17 [ 2017-10-09 ] |
Production Due Date | 12/Oct/2017 | 19/Oct/2017 |
-
- Time Spent:
- 2h
-
LB Testing and Discussion with Abhilash
Time Spent | 113.5h [ 408600 ] | 115.5h [ 415800 ] |
Worklog Id | 83510 [ 83510 ] |
Labels | SA_Utility |
Stage Due Date | 9/Oct/17 [ 2017-10-09 ] | 17/Oct/17 [ 2017-10-17 ] |
Production Due Date | 19/Oct/2017 | 25/Oct/2017 |
Stage Due Date | 17/Oct/17 [ 2017-10-17 ] | 24/Oct/17 [ 2017-10-24 ] |
Production Due Date | 25/Oct/2017 | 04/Nov/2017 |
Item State | Parent values: LB QA(10201)Level 1 values: In Testing(10210) | Parent values: LB QA(10201)Level 1 values: Re-open(10212) |
Status | Local Testing [ 10200 ] | Reopen in Local [ 10018 ] |
Assignee | Priya Dhamande [ priya.dhamande ] | Abhilash Warkari [ abhilash.warkari ] |
Time Spent | 115.5h [ 415800 ] | 120.5h [ 433800 ] |
Worklog Id | 86514 [ 86514 ] |
Time Spent | 120.5h [ 433800 ] | 122.5h [ 441000 ] |
Worklog Id | 86530 [ 86530 ] |
Time Spent | 122.5h [ 441000 ] | 124.5h [ 448200 ] |
Worklog Id | 86541 [ 86541 ] |
Assignee | Abhilash Warkari [ abhilash.warkari ] | Priya Dhamande [ priya.dhamande ] |
Item State | Parent values: LB QA(10201)Level 1 values: Re-open(10212) | Parent values: LB QA(10201)Level 1 values: In Testing(10210) |
Time Spent | 124.5h [ 448200 ] | 127h [ 457200 ] |
Worklog Id | 88093 [ 88093 ] |
Status | Reopen in Local [ 10018 ] | In Development [ 10007 ] |
Status | In Development [ 10007 ] | Local Testing [ 10200 ] |
Status | Local Testing [ 10200 ] | Pending for Stage Approval [ 10300 ] |
Status | Pending for Stage Approval [ 10300 ] | Approved for Stage [ 10030 ] |
Item State | Parent values: LB QA(10201)Level 1 values: In Testing(10210) | Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213) |
Time Spent | 127h [ 457200 ] | 137h [ 493200 ] |
Worklog Id | 88093 [ 88093 ] |
Remaining Estimate | 0h [ 0 ] | 11.5h [ 41400 ] |
Time Spent | 137h [ 493200 ] | 125.5h [ 451800 ] |
Worklog Id | 88093 [ 88093 ] |
Remaining Estimate | 11.5h [ 41400 ] | 9h [ 32400 ] |
Time Spent | 125.5h [ 451800 ] | 128h [ 460800 ] |
Worklog Id | 88344 [ 88344 ] |
Remaining Estimate | 9h [ 32400 ] | 8h [ 28800 ] |
Time Spent | 128h [ 460800 ] | 129h [ 464400 ] |
Worklog Id | 88345 [ 88345 ] |
Remaining Estimate | 8h [ 28800 ] | 9h [ 32400 ] |
Time Spent | 129h [ 464400 ] | 128h [ 460800 ] |
Worklog Id | 88093 [ 88093 ] | |
Worklog Time Spent | 1h [ 3600 ] |
Item State | Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213) | Parent values: LB QA(10201)Level 1 values: On Hold(10211) |
Link | This issue causes MOB-2739 [ MOB-2739 ] |
Resolution | Done [ 10000 ] | |
Status | Approved for Stage [ 10030 ] | Resolution Setting [ 11616 ] |
Transition | Time In Source Status | Execution Times |
---|
|
150d 20h 34m | 1 |
|
2s | 1 |
|
2s | 1 |
|
19d 8h 6m | 1 |
|
7d 19h 34m | 1 |
|
63d 18h 56m | 2 |
|
3s | 1 |
|
3s | 1 |
|
196d 17h 42m | 1 |
to be started from Wednesday, 26th July 2017.
Cc: Amruta Lohiya Jyoti Mayne Vijay Siddha