GI is not working for LTD.
If GI is not required for LTD benefit type then it should be Invisible from plan design.
Field | Original Value | New Value |
---|---|---|
Summary | Enroll Now -> LTD | Enroll Now -> LTD -> Issue with GI |
Issue Importance | Must Have [ 11800 ] |
Assignee | Satya [ ID10004 ] | Amruta Lohiya [ amruta.baheti ] |
Assignee | Amruta Lohiya [ amruta.baheti ] | Umesh Kadam [ umesh.kadam ] |
Assignee | Umesh Kadam [ umesh.kadam ] | Amruta Lohiya [ amruta.baheti ] |
Assignee | Amruta Lohiya [ amruta.baheti ] | Harshawardhan Phalake [ harshawardhan ] |
Status | Open [ 1 ] | In Development [ 10007 ] |
Code Reviewed By | Amruta Lohiya [ 11906 ] |
Item State | Parent values: Development(10200)Level 1 values: In Analysis(10204) |
Item State | Parent values: Development(10200)Level 1 values: In Analysis(10204) | Parent values: Development(10200)Level 1 values: Ready for Review(10208) |
Item State | Parent values: Development(10200)Level 1 values: Ready for Review(10208) | Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) |
Assignee | Harshawardhan Phalake [ harshawardhan ] | Hrishikesh Deshpande [ hrishikesh.deshpande ] |
Status | In Development [ 10007 ] | Local Testing [ 10200 ] |
Production Due Date | 04/Aug/2016 | |
Stage Due Date | 3/Aug/16 [ 2016-08-03 ] |
Item State | Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) | Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213) |
Item State | Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213) | Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602) |
Status | Local Testing [ 10200 ] | Stage Testing [ 10201 ] |
Resolution | Unresolved [ 10200 ] | |
Status | Stage Testing [ 10201 ] | Reopen in Stage [ 10023 ] |
Assignee | Hrishikesh Deshpande [ hrishikesh.deshpande ] | Harshawardhan Phalake [ harshawardhan ] |
Status | Reopen in Stage [ 10023 ] | In Development [ 10007 ] |
Status | In Development [ 10007 ] | Local Testing [ 10200 ] |
Assignee | Harshawardhan Phalake [ harshawardhan ] | Hrishikesh Deshpande [ hrishikesh.deshpande ] |
Status | Local Testing [ 10200 ] | Stage Testing [ 10201 ] |
Item State | Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602) | Parent values: Stage QA(10202)Level 1 values: Ready for Production(10217) |
Item State | Parent values: Stage QA(10202)Level 1 values: Ready for Production(10217) | Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602) |
Item State | Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602) | Parent values: Stage QA(10202)Level 1 values: Ready for Production(10217) |
Developer | Harshawardhan Phalake [ harshawardhan ] |
Item State | Parent values: Stage QA(10202)Level 1 values: Ready for Production(10217) | Parent values: Production QA(10203)Level 1 values: Production Deployed(10221) |
Status | Stage Testing [ 10201 ] | Production Testing [ 10202 ] |
Resolution | Unresolved [ 10200 ] | Fixed [ 1 ] |
Status | Production Testing [ 10202 ] | Production Complete [ 10028 ] |
Item State | Parent values: Production QA(10203)Level 1 values: Production Deployed(10221) | Parent values: Production Complete(10222) |
Status | Production Complete [ 10028 ] | Closed [ 6 ] |
Transition | Time In Source Status | Execution Times |
---|
|
9d 2h | 1 |
|
2s | 1 |
|
33m 41s | 1 |
|
11d 3h 20m | 2 |
|
1d 21h 7m | 2 |
|
5d 19h 52m | 1 |
|
15s | 1 |
|
8s | 1 |
Cc: Amruta Lohiya
Hi Hrishikesh Deshpande,
Please Test the above scenario on LB as it is deployed on LB.
As GI is not required for LTD benefit type so we removed the GI functionality from Plan Design for LTD.
Thanks and Regards,
Harshawardhan.