Uploaded image for project: 'WORKTERRA'
  1. WORKTERRA
  2. WT-10963

OE Dashboard - 1 Feeds not reflecting as per schedule on/off - Schedule changed from EDI Utility

    Details

    • Type: Bug
    • Status: Closed
    • Priority: Medium
    • Resolution: Done
    • Affects Version/s: None
    • Fix Version/s: None
    • Component/s: None
    • Labels:
      None
    • Environment:
      Stage
    • Bug Severity:
      Medium
    • Module:
      BenAdmin - Export
    • Reported by:
      Harbinger
    • Item State:
      Production Complete - Closed

      Description

      Description :

      OE Dashboard is not reflecting feeds as per Schedule on/off settings.

      If the schedule of the feeds is changed i.e on/off using EDI Utility then they are not reflecting on the OE Dashboard.

      Thanks,
      S Prashant.
      -------------------------------------------------------------------------------

      Ganesh Sadawarte Vinayak Kulkarni Yogita Bhadane Amit Thorve

        Attachments

          Issue Links

            Activity

            Prashant.samal Prashant Samal (Inactive) created issue -
            Ganesh.sadawarte Ganesh Sadawarte (Inactive) made changes -
            Field Original Value New Value
            Status Open [ 1 ] In Development [ 10007 ]
            Ganesh.sadawarte Ganesh Sadawarte (Inactive) made changes -
            Dev Estimates 28
            Developer Ganesh Sadawarte [ ganesh.sadawarte ]
            Ganesh.sadawarte Ganesh Sadawarte (Inactive) made changes -
            Remaining Estimate 30h [ 108000 ]
            Original Estimate 30h [ 108000 ]
            Ganesh.sadawarte Ganesh Sadawarte (Inactive) made changes -
            Remaining Estimate 30h [ 108000 ] 23h 50m [ 85800 ]
            Time Spent 6h 10m [ 22200 ]
            Worklog Id 77225 [ 77225 ]
            Ganesh.sadawarte Ganesh Sadawarte (Inactive) made changes -
            Remaining Estimate 23h 50m [ 85800 ] 23.5h [ 84600 ]
            Time Spent 6h 10m [ 22200 ] 6.5h [ 23400 ]
            Worklog Id 77225 [ 77225 ]
            Ganesh.sadawarte Ganesh Sadawarte (Inactive) made changes -
            Remaining Estimate 23.5h [ 84600 ] 23.25h [ 83700 ]
            Time Spent 6.5h [ 23400 ] 6.75h [ 24300 ]
            Worklog Id 77225 [ 77225 ]
            Ganesh.sadawarte Ganesh Sadawarte (Inactive) made changes -
            Remaining Estimate 23.25h [ 83700 ] 16.25h [ 58500 ]
            Time Spent 6.75h [ 24300 ] 13.75h [ 49500 ]
            Worklog Id 77313 [ 77313 ]
            Ganesh.sadawarte Ganesh Sadawarte (Inactive) made changes -
            Code Review Date 07/Sep/2017
            Code Reviewed By Vinalyak Kulkarni [ 12100 ]
            Dev Due Date 07/Sep/2017
            Ganesh.sadawarte Ganesh Sadawarte (Inactive) made changes -
            Attachment AffectedFiles.txt [ 60902 ]
            Ganesh.sadawarte Ganesh Sadawarte (Inactive) made changes -
            Item State Parent values: Development(10200)Level 1 values: Ready for Local Testing(10209)
            Ganesh.sadawarte Ganesh Sadawarte (Inactive) made changes -
            Remaining Estimate 16.25h [ 58500 ] 11.25h [ 40500 ]
            Time Spent 13.75h [ 49500 ] 18.75h [ 67500 ]
            Worklog Id 77335 [ 77335 ]
            khandu.kshirsagar Khandu Kshirsagar (Inactive) made changes -
            Item State Parent values: Development(10200)Level 1 values: Ready for Local Testing(10209) Parent values: LB QA(10201)Level 1 values: LB Deployed(11600)
            Ganesh.sadawarte Ganesh Sadawarte (Inactive) made changes -
            Link This issue relates to WT-10480 [ WT-10480 ]
            Ganesh.sadawarte Ganesh Sadawarte (Inactive) made changes -
            Assignee Ganesh Sadawarte [ ganesh.sadawarte ] Swapnil Eksambekar [ swapnil.eksambekar ]
            swapnil.eksambekar Swapnil Eksambekar (Inactive) made changes -
            Status In Development [ 10007 ] Local Testing [ 10200 ]
            Prashant.samal Prashant Samal (Inactive) made changes -
            Remaining Estimate 11.25h [ 40500 ] 8.75h [ 31500 ]
            Time Spent 18.75h [ 67500 ] 21.25h [ 76500 ]
            Worklog Id 77499 [ 77499 ]
            swapnil.eksambekar Swapnil Eksambekar (Inactive) made changes -
            Item State Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) Parent values: LB QA(10201)Level 1 values: In Testing(10210)
            swapnil.eksambekar Swapnil Eksambekar (Inactive) made changes -
            Item State Parent values: LB QA(10201)Level 1 values: In Testing(10210) Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213)
            swapnil.eksambekar Swapnil Eksambekar (Inactive) made changes -
            Remaining Estimate 8.75h [ 31500 ] 8.25h [ 29700 ]
            Time Spent 21.25h [ 76500 ] 21.75h [ 78300 ]
            Worklog Id 77517 [ 77517 ]
            khandu.kshirsagar Khandu Kshirsagar (Inactive) made changes -
            Item State Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213) Parent values: LB QA(10201)Level 1 values: LB Deployed(11600)
            Prashant.samal Prashant Samal (Inactive) made changes -
            Remaining Estimate 8.25h [ 29700 ] 4.25h [ 15300 ]
            Time Spent 21.75h [ 78300 ] 25.75h [ 92700 ]
            Worklog Id 77999 [ 77999 ]
            swapnil.eksambekar Swapnil Eksambekar (Inactive) made changes -
            Item State Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213)
            yogita.bhadane Yogita Bhadane (Inactive) made changes -
            Link This issue relates to WT-10863 [ WT-10863 ]
            khandu.kshirsagar Khandu Kshirsagar (Inactive) made changes -
            Item State Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213) Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602)
            swapnil.eksambekar Swapnil Eksambekar (Inactive) made changes -
            Item State Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602) Parent values: Stage QA(10202)Level 1 values: Ready for Production(10217)
            swapnil.eksambekar Swapnil Eksambekar (Inactive) made changes -
            Status Local Testing [ 10200 ] Stage Testing [ 10201 ]
            swapnil.eksambekar Swapnil Eksambekar (Inactive) made changes -
            Remaining Estimate 4.25h [ 15300 ] 3.55h [ 12780 ]
            Time Spent 25.75h [ 92700 ] 26.45h [ 95220 ]
            Worklog Id 80341 [ 80341 ]
            Vinayak.Kulkarni Vinayak Kulkarni (Inactive) made changes -
            Remaining Estimate 3.55h [ 12780 ] 0h [ 0 ]
            Time Spent 26.45h [ 95220 ] 30.45h [ 109620 ]
            Worklog Id 80820 [ 80820 ]
            rakeshr Rakesh Roy (Inactive) made changes -
            Production Due Date 26/Sep/2017
            rakeshr Rakesh Roy (Inactive) made changes -
            QA Swapnil Eksambekar [ swapnil.eksambekar ]
            Ganesh.sadawarte Ganesh Sadawarte (Inactive) made changes -
            Item State Parent values: Stage QA(10202)Level 1 values: Ready for Production(10217) Parent values: Production QA(10203)Level 1 values: Production Deployed(10221)
            swapnil.eksambekar Swapnil Eksambekar (Inactive) made changes -
            Item State Parent values: Production QA(10203)Level 1 values: Production Deployed(10221) Parent values: Production QA(10203)Level 1 values: In Testing(10218)
            swapnil.eksambekar Swapnil Eksambekar (Inactive) made changes -
            Status Stage Testing [ 10201 ] Production Testing [ 10202 ]
            swapnil.eksambekar Swapnil Eksambekar (Inactive) made changes -
            Resolution Fixed [ 1 ]
            Status Production Testing [ 10202 ] Production Complete [ 10028 ]
            swapnil.eksambekar Swapnil Eksambekar (Inactive) made changes -
            Status Production Complete [ 10028 ] Closed [ 6 ]
            swapnil.eksambekar Swapnil Eksambekar (Inactive) made changes -
            Item State Parent values: Production QA(10203)Level 1 values: In Testing(10218) Parent values: Production Complete(10222)Level 1 values: Closed(10223)
            swapnil.eksambekar Swapnil Eksambekar (Inactive) made changes -
            Time Spent 30.45h [ 109620 ] 30.95h [ 111420 ]
            Worklog Id 81754 [ 81754 ]
            satyap Satya made changes -
            Environment_New Stage [ 18443 ]

              People

              Assignee:
              swapnil.eksambekar Swapnil Eksambekar (Inactive)
              Reporter:
              Prashant.samal Prashant Samal (Inactive)
              EDI Analyst 1:
              Prashant Samal (Inactive)
              Developer:
              Ganesh Sadawarte (Inactive)
              QA:
              Swapnil Eksambekar (Inactive)
              Votes:
              0 Vote for this issue
              Watchers:
              4 Start watching this issue

                Dates

                Created:
                Updated:
                Resolved:
                Dev Due Date:
                Production Due Date:
                Code Review Date:

                  Time Tracking

                  Estimated:
                  Original Estimate - 30h Original Estimate - 30h
                  30h
                  Remaining:
                  Remaining Estimate - 0h
                  0h
                  Logged:
                  Time Spent - 30.95h
                  30.95h