Uploaded image for project: 'WORKTERRA'
  1. WORKTERRA
  2. WT-11767

ACA 2018 Need to remove download confirmation pop-up after the processing of 1095-C report

    Details

    • Type: Change Request
    • Status: Production Complete
    • Priority: Medium
    • Resolution: Done
    • Affects Version/s: None
    • Fix Version/s: None
    • Component/s: ACA
    • Labels:
    • Environment:
      Production
    • Module:
      ACA
    • Reported by:
      Harbinger
    • Company:
      All Clients/Multiple Clients
    • Item State:
      Production Complete - Closed
    • Issue Importance:
      Good To Have
    • Feature Category:
      Integration
    • Severity:
      Simple

      Description

      Current Implementation : After the processing of 1095B/C report, a Ok/Cancel popup is shown asking Do you want to download the file.If user clicks on Ok,downloading of zip file starts. There can be wastage of user's time,if the Employee count is not as per expected which he would know only after downloading the zip files.
      New Implementation : This change is done for better user experience. Download of 1095C forms should happen from one point only,i.e from Show Runs-> Download Zip. If user downloads it from Show Runs-> Download Zip, he would get full information of that run along with EE count.
      CC Nandkumar Prabhakar Karlekar Ramya Tantry Smita Pawar

        Attachments

        1. 1095_c.png
          1095_c.png
          195 kB
        2. Confirmation pop up.png
          Confirmation pop up.png
          170 kB
        3. WT-11767.xls
          12 kB

          Activity

          Transition Time In Source Status Execution Times
          Kumar Chhajed (Inactive) made transition -
          New Request Pending for Approval
          4h 19m 1
          Kumar Chhajed (Inactive) made transition -
          Pending for Approval Approved for Development
          6s 1
          Kumar Chhajed (Inactive) made transition -
          Approved for Development In Development
          2s 1
          Kumar Chhajed (Inactive) made transition -
          In Development In LB Testing
          22h 24m 1
          Sachin Hingole (Inactive) made transition -
          In LB Testing Pending for Stage Approval
          19d 22h 40m 1
          Sachin Hingole (Inactive) made transition -
          Pending for Stage Approval Approved for Stage
          2m 38s 1
          Sachin Hingole (Inactive) made transition -
          Approved for Stage Stage Testing
          4m 56s 1
          Smita Pawar (Inactive) made transition -
          Stage Testing Pending for Production Approval
          11d 3h 25m 1
          Smita Pawar (Inactive) made transition -
          Pending for Production Approval Approved for production
          4s 1
          Smita Pawar (Inactive) made transition -
          Approved for production In Production Testing
          3s 1
          Smita Pawar (Inactive) made transition -
          In Production Testing Production Complete
          2d 21h 18m 1

            People

            Assignee:
            smita.pawar Smita Pawar (Inactive)
            Reporter:
            kumar.chhajed Kumar Chhajed (Inactive)
            Developer:
            Kumar Chhajed (Inactive)
            QA:
            Smita Pawar (Inactive)
            Votes:
            0 Vote for this issue
            Watchers:
            4 Start watching this issue

              Dates

              Created:
              Updated:
              Resolved:
              Pre-Prod Due Date:
              Production Due Date:
              Code Review Date:

                Time Tracking

                Estimated:
                Original Estimate - 8h Original Estimate - 8h
                8h
                Remaining:
                Remaining Estimate - 0h
                0h
                Logged:
                Time Spent - 9.75h
                9.75h