Uploaded image for project: 'WORKTERRA'
  1. WORKTERRA
  2. WT-5928

Aurico/WT Integration Staging Details

    Details

    • Type: Enhancement
    • Status: Production Complete
    • Priority: Medium
    • Resolution: Done
    • Affects Version/s: None
    • Fix Version/s: None
    • Component/s: Platform
    • Labels:
      None
    • Module:
      Aurico integration
    • Reported by:
      Support
    • Item State:
      Production Complete - Closed

      Description

      WORKTERRA to integrate with Aurico (Background Check Service)

        Attachments

          Issue Links

            Activity

            samir Samir created issue -
            Hide
            samir Samir added a comment -

            Attached are the documents for Aurico integration

            Aurico is one implementation this integration can be done with an other service provider

            Show
            samir Samir added a comment - Attached are the documents for Aurico integration Aurico is one implementation this integration can be done with an other service provider
            samir Samir made changes -
            Field Original Value New Value
            Assignee Vijay Siddha [ vijays ] Samir [ samir ]
            samir Samir made changes -
            samir Samir made changes -
            Hide
            samir Samir added a comment -
            Show
            samir Samir added a comment - Saurabh Sablaka Nagini Indugula
            Hide
            samir Samir added a comment -

            Saurabh Sablaka tech lead
            Varsha Shejawal :Admin screen development
            Vikas Pawar web service integration development

            Show
            samir Samir added a comment - Saurabh Sablaka tech lead Varsha Shejawal :Admin screen development Vikas Pawar web service integration development
            samir Samir made changes -
            Assignee Samir [ samir ] Saurabh Sablaka [ saurabh.sablaka ]
            diana Diana Wong (Inactive) made changes -
            Status New Request [ 10029 ] Pending for Approval [ 10002 ]
            samir Samir made changes -
            Status Pending for Approval [ 10002 ] Approved for Development [ 10003 ]
            samir Samir made changes -
            Status Approved for Development [ 10003 ] In Development [ 10007 ]
            saurabh.sablaka Saurabh Sablaka (Inactive) made changes -
            Hide
            saurabh.sablaka Saurabh Sablaka (Inactive) added a comment -

            Attached is the Understanding document with development workflow & task breakdown for WT - AURICO Integration.
            WORKTERRA_Aurico Integration_Understanding document.doc

            As of now, we have successfully submitted request data to Aurico staging site and also recorded Initial responses in Workterra. We are now stuck on completing entire workflow which needs credentials to select Background Check Package and initiate request for employee.

            Show
            saurabh.sablaka Saurabh Sablaka (Inactive) added a comment - Attached is the Understanding document with development workflow & task breakdown for WT - AURICO Integration. WORKTERRA_Aurico Integration_Understanding document.doc As of now, we have successfully submitted request data to Aurico staging site and also recorded Initial responses in Workterra. We are now stuck on completing entire workflow which needs credentials to select Background Check Package and initiate request for employee.
            saurabh.sablaka Saurabh Sablaka (Inactive) made changes -
            Component/s Platform [ 10006 ]
            Description
            WORKTERRA to integrate with Aurico (Background Check Service)
            WORKTERRA to integrate with Aurico (Background Check Service)
            Dev Due Date 11/Nov/2016
            Developer Saurabh Sablaka [ saurabh.sablaka ]
            Item State Parent values: Development(10200)Level 1 values: In Progress(10206)
            Module Parent values: BenAdmin(10100) Parent values: Platform(10106)
            QA Prasad Pise [ prasadp ]
            saurabh.sablaka Saurabh Sablaka (Inactive) made changes -
            Link This issue relates to WT-5941 [ WT-5941 ]
            saurabh.sablaka Saurabh Sablaka (Inactive) made changes -
            Link This issue relates to WT-5942 [ WT-5942 ]
            Hide
            saurabh.sablaka Saurabh Sablaka (Inactive) added a comment -

            Status Update:
            We have completed the tasks defined in current scope for Aurico Integration. We are able to “Initiate background Check” and then receive back the “Status Responses”. Confirmed the same with Paolo over call and also checked on Status responses getting updated in Workterra.

            Show
            saurabh.sablaka Saurabh Sablaka (Inactive) added a comment - Status Update: We have completed the tasks defined in current scope for Aurico Integration. We are able to “Initiate background Check” and then receive back the “Status Responses”. Confirmed the same with Paolo over call and also checked on Status responses getting updated in Workterra.
            shyam.sharma shyam sharma (Inactive) made changes -
            Sprint Aurico integration - Sprint 1 [ 33 ]
            saurabh.sablaka Saurabh Sablaka (Inactive) made changes -
            Link This issue relates to WT-6522 [ WT-6522 ]
            saurabh.sablaka Saurabh Sablaka (Inactive) made changes -
            Link This issue relates to WT-6561 [ WT-6561 ]
            Hide
            samir Samir added a comment -
            Show
            samir Samir added a comment - WT-6561
            saurabh.sablaka Saurabh Sablaka (Inactive) made changes -
            Status In Development [ 10007 ] Local Testing [ 10200 ]
            saurabh.sablaka Saurabh Sablaka (Inactive) made changes -
            Status Local Testing [ 10200 ] Pending for Stage Approval [ 10300 ]
            saurabh.sablaka Saurabh Sablaka (Inactive) made changes -
            Status Pending for Stage Approval [ 10300 ] Approved for Stage [ 10030 ]
            saurabh.sablaka Saurabh Sablaka (Inactive) made changes -
            Status Approved for Stage [ 10030 ] Stage Testing [ 10201 ]
            saurabh.sablaka Saurabh Sablaka (Inactive) made changes -
            Status Stage Testing [ 10201 ] Pending for Production Approval [ 10301 ]
            saurabh.sablaka Saurabh Sablaka (Inactive) made changes -
            Status Pending for Production Approval [ 10301 ] Approved for production [ 10034 ]
            saurabh.sablaka Saurabh Sablaka (Inactive) made changes -
            Status Approved for production [ 10034 ] Production Testing [ 10202 ]
            saurabh.sablaka Saurabh Sablaka (Inactive) made changes -
            Item State Parent values: Development(10200)Level 1 values: In Progress(10206) Parent values: Production QA(10203)Level 1 values: In Testing(10218)
            saurabh.sablaka Saurabh Sablaka (Inactive) made changes -
            saurabh.sablaka Saurabh Sablaka (Inactive) made changes -
            Assignee Saurabh Sablaka [ saurabh.sablaka ] Samir [ samir ]
            shyam.sharma shyam sharma (Inactive) made changes -
            Sprint WT Sprint 20 [ 33 ]
            rakeshr Rakesh Roy (Inactive) made changes -
            Resolution Fixed [ 1 ]
            Status Production Testing [ 10202 ] Production Complete [ 10028 ]
            rakeshr Rakesh Roy (Inactive) made changes -
            Item State Parent values: Production QA(10203)Level 1 values: In Testing(10218) Parent values: Production Complete(10222)Level 1 values: Closed(10223)
            saurabh.sablaka Saurabh Sablaka (Inactive) made changes -
            Module Parent values: Platform(10106) Parent values: Aurico integration(14301)
            Transition Time In Source Status Execution Times
            Diana Wong (Inactive) made transition -
            New Request Pending for Approval
            2d 5h 6m 1
            Samir made transition -
            Pending for Approval Approved for Development
            12h 45m 1
            Samir made transition -
            Approved for Development In Development
            1m 2s 1
            Saurabh Sablaka (Inactive) made transition -
            In Development In LB Testing
            39d 20h 25m 1
            Saurabh Sablaka (Inactive) made transition -
            In LB Testing Pending for Stage Approval
            3s 1
            Saurabh Sablaka (Inactive) made transition -
            Pending for Stage Approval Approved for Stage
            2s 1
            Saurabh Sablaka (Inactive) made transition -
            Approved for Stage Stage Testing
            2s 1
            Saurabh Sablaka (Inactive) made transition -
            Stage Testing Pending for Production Approval
            2s 1
            Saurabh Sablaka (Inactive) made transition -
            Pending for Production Approval Approved for production
            2s 1
            Saurabh Sablaka (Inactive) made transition -
            Approved for production In Production Testing
            4s 1
            Rakesh Roy (Inactive) made transition -
            In Production Testing Production Complete
            24d 19h 15m 1

              People

              Assignee:
              samir Samir
              Reporter:
              samir Samir
              Developer:
              Saurabh Sablaka (Inactive)
              QA:
              Prasad Pise (Inactive)
              Votes:
              0 Vote for this issue
              Watchers:
              4 Start watching this issue

                Dates

                Created:
                Updated:
                Resolved:
                Dev Due Date: