Details

    • Type: Support Activity
    • Status: Resolved
    • Priority: Critical
    • Resolution: Done
    • Affects Version/s: None
    • Fix Version/s: None
    • Component/s: ACA
    • Labels:
      None
    • Support Task Type:
      ACA IRS Report
    • Environment:
      Production
    • Reported by:
      Client
    • Company:
      Elite Staffing
    • Module:
      ACA - 2017

      Description

      1095C report. when i run this report i get a server error and no report pulls out. Please help pull the report. i see the ACA customization is set so i am not sure if the settings are incorrect on this setting page or if the report is just too large because the size of the group. i need to get the reports out to the client ASAP, 12/13, to start reviewing. i would like to review this first prior to them going to the client. Please help assist. let me know if any settings are wrong or if i just always have to go through development to run the reports because of the size of the group.

      this is the ACA timeline we are working off of, see attached.

      CC:Satya Lorena.Nava@ebsbenefits.com

        Attachments

          Activity

          ramya.tantry Ramya Tantry (Inactive) logged work - 14/Dec/16 06:07 AM - edited
          • Time Spent:
            2h
             

            Check ACA Customization.
            verify EIN mapping
            Verify Measurement and stability rules.
            Furnish 1095C report.
            verify Sample pdf
            verify Analysis report.

          ramya.tantry Ramya Tantry (Inactive) logged work - 15/Dec/16 04:20 PM - edited
          • Time Spent:
            1h
             

            Analysis of client query
            Draft reply

          sachin.hingole Sachin Hingole (Inactive) logged work - 19/Dec/16 11:41 AM
          • Time Spent:
            0.5h
             
            <No comment>
          ramya.tantry Ramya Tantry (Inactive) logged work - 19/Dec/16 07:09 PM
          • Time Spent:
            0.5h
             

            Analysis report download.

          mahendra.mungase Mahendra Mungase (Inactive) logged work - 10/Feb/17 01:25 PM
          • Time Spent:
            4h
             

            Customization and Run 95C

          mahendra.mungase Mahendra Mungase (Inactive) logged work - 14/Feb/17 07:18 AM
          • Time Spent:
            3h
             

            1095C run

          rutuja.chilwar Rutuja Chilwar (Inactive) logged work - 14/Feb/17 06:37 PM
          • Time Spent:
            3h
             
            <No comment>
          mahendra.mungase Mahendra Mungase (Inactive) logged work - 15/Feb/17 07:25 AM
          • Time Spent:
            4h
             

            95C Report re run

          rutuja.chilwar Rutuja Chilwar (Inactive) logged work - 15/Feb/17 11:31 AM - edited
          • Time Spent:
            5h
             

            ACA report run

          mahendra.mungase Mahendra Mungase (Inactive) logged work - 15/Feb/17 01:18 PM - edited
          • Time Spent:
            1h
             

            Follow up of 1095C

          nandkumar Nandkumar Prabhakar Karlekar (Inactive) logged work - 16/Feb/17 01:01 PM
          • Time Spent:
            2h
             
            <No comment>
          mahendra.mungase Mahendra Mungase (Inactive) logged work - 16/Feb/17 01:20 PM
          • Time Spent:
            0.5h
             

            Followup of 1095C

          rutuja.chilwar Rutuja Chilwar (Inactive) logged work - 17/Feb/17 05:59 AM
          • Time Spent:
            4h
             

            Run & Download report

          kumar.chhajed Kumar Chhajed (Inactive) logged work - 17/Feb/17 09:23 AM
          • Time Spent:
            3.5h
             

            Run 1095C Reports

          smita.pawar Smita Pawar (Inactive) logged work - 17/Feb/17 01:46 PM
          • Time Spent:
            4h
             

            Forms download
            Internal discussion
            Reports uploading on

          nandkumar Nandkumar Prabhakar Karlekar (Inactive) logged work - 17/Feb/17 02:12 PM
          • Time Spent:
            2h
             
            <No comment>
          mahendra.mungase Mahendra Mungase (Inactive) logged work - 22/Feb/17 12:22 PM
          • Time Spent:
            5h
             

            195C audit and monitoring

          kumar.chhajed Kumar Chhajed (Inactive) logged work - 22/Feb/17 02:01 PM
          • Time Spent:
            4h
             

            Run 1095C reports
            Internal discussion with Nandu

          rutuja.chilwar Rutuja Chilwar (Inactive) logged work - 23/Feb/17 04:43 AM
          • Time Spent:
            2.5h
             
            <No comment>
          rutuja.chilwar Rutuja Chilwar (Inactive) logged work - 23/Feb/17 09:22 AM
          • Time Spent:
            3h
             
            <No comment>
          mahendra.mungase Mahendra Mungase (Inactive) logged work - 23/Feb/17 12:31 PM
          • Time Spent:
            6h
             

            95C analysis report down load

          kumar.chhajed Kumar Chhajed (Inactive) logged work - 23/Feb/17 01:53 PM - edited
          • Time Spent:
            8.5h
             

            Run 1095C Reports,Consolidated reports and Analysis Report
            Upload on FTP server

          nandkumar Nandkumar Prabhakar Karlekar (Inactive) logged work - 24/Feb/17 01:14 AM
          • Time Spent:
            2h
             
            <No comment>
          mahendra.mungase Mahendra Mungase (Inactive) logged work - 24/Feb/17 12:33 PM
          • Time Spent:
            1h
             

            Anlysis report download

          kumar.chhajed Kumar Chhajed (Inactive) logged work - 24/Feb/17 01:52 PM
          • Time Spent:
            3h
             

            Run 1095C Reports
            Upload on FTP
            Draft reply

          nandkumar Nandkumar Prabhakar Karlekar (Inactive) logged work - 25/Feb/17 01:27 AM
          • Time Spent:
            2h
             
            <No comment>
          kumar.chhajed Kumar Chhajed (Inactive) logged work - 27/Feb/17 01:27 PM
          • Time Spent:
            6h
             

            Move Data from HSPL to Main Company

          nandkumar Nandkumar Prabhakar Karlekar (Inactive) logged work - 28/Feb/17 01:29 AM
          • Time Spent:
            6h
             
            <No comment>
          nandkumar Nandkumar Prabhakar Karlekar (Inactive) logged work - 08/Mar/17 01:45 AM
          • Time Spent:
            4h
             
            <No comment>

            People

            Assignee:
            jennifer.leugers Jennifer Leugers
            Reporter:
            amjohnson Amannda Johnson
            Votes:
            0 Vote for this issue
            Watchers:
            11 Start watching this issue

              Dates

              Created:
              Updated:
              Resolved:

                Time Tracking

                Estimated:
                Original Estimate - 7h Original Estimate - 7h
                7h
                Remaining:
                Time Spent - 93h Remaining Estimate - 2h
                2h
                Logged:
                Time Spent - 93h Remaining Estimate - 2h
                93h