Type:
Support Activity
-
Status: Resolved
-
Priority:
Medium
-
Resolution: Cancelled
-
Affects Version/s: None
-
Fix Version/s: None
-
Component/s: Recruit
-
Labels:None
-
Support Task Type:Configuration
-
Environment:Others
-
Reported by:Harbinger
-
Company:New Facility Not Added
-
Module:Recruit
Field | Original Value | New Value |
---|---|---|
Assignee | Samir [ samir ] | Jaideep Vinchurkar [ jaideep.vinchurkar ] |
Remaining Estimate | 24h [ 86400 ] | 15h [ 54000 ] |
Time Spent | 9h [ 32400 ] | |
Worklog Id | 17951 [ 17951 ] |
Remaining Estimate | 15h [ 54000 ] | 5h [ 18000 ] |
Time Spent | 9h [ 32400 ] | 19h [ 68400 ] |
Worklog Id | 17954 [ 17954 ] |
-
- Time Spent:
- 10h
-
Development with Jaideep.
Item State | Parent values: Development(10200)Level 1 values: In Progress(10206) | Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) |
Assignee | Jaideep Vinchurkar [ jaideep.vinchurkar ] | Rashmita Dudhe [ rashmita.dudhe ] |
Item State | Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) | Parent values: LB QA(10201)Level 1 values: Re-open(10212) |
Assignee | Rashmita Dudhe [ rashmita.dudhe ] | Jaideep Vinchurkar [ jaideep.vinchurkar ] |
Remaining Estimate | 5h [ 18000 ] | 3h [ 10800 ] |
Time Spent | 19h [ 68400 ] | 21h [ 75600 ] |
Worklog Id | 18049 [ 18049 ] |
Assignee | Jaideep Vinchurkar [ jaideep.vinchurkar ] | Rashmita Dudhe [ rashmita.dudhe ] |
Item State | Parent values: LB QA(10201)Level 1 values: Re-open(10212) | Parent values: LB QA(10201)Level 1 values: In Testing(10210) |
Summary | Recruit import - support for column wise import | Paycheck import - support for column wise import |
Item State | Parent values: LB QA(10201)Level 1 values: In Testing(10210) | Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213) |
Status | New Request [ 10029 ] | Pending for Approval [ 10002 ] |
Status | Pending for Approval [ 10002 ] | Approved for Development [ 10003 ] |
Status | Approved for Development [ 10003 ] | In Development [ 10007 ] |
Status | In Development [ 10007 ] | Local Testing [ 10200 ] |
Attachment | WT-7632_Testcase.xls [ 36965 ] |
Remaining Estimate | 3h [ 10800 ] | 9h [ 32400 ] |
Original Estimate | 24h [ 86400 ] | 30h [ 108000 ] |
Remaining Estimate | 9h [ 32400 ] | 8h [ 28800 ] |
Time Spent | 21h [ 75600 ] | 22h [ 79200 ] |
Worklog Id | 18169 [ 18169 ] |
Remaining Estimate | 8h [ 28800 ] | 5h [ 18000 ] |
Time Spent | 22h [ 79200 ] | 25h [ 90000 ] |
Worklog Id | 18170 [ 18170 ] |
Remaining Estimate | 5h [ 18000 ] | 7h [ 25200 ] |
Time Spent | 25h [ 90000 ] | 23h [ 82800 ] |
Worklog Id | 18049 [ 18049 ] | |
Worklog Time Spent | 2h [ 7200 ] |
Remaining Estimate | 7h [ 25200 ] | 6h [ 21600 ] |
Time Spent | 23h [ 82800 ] | 24h [ 86400 ] |
Worklog Id | 18169 [ 18169 ] |
Item State | Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213) | Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602) |
Item State | Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602) | Parent values: Stage QA(10202)Level 1 values: On Hold(10215) |
Remaining Estimate | 6h [ 21600 ] | 5.5h [ 19800 ] |
Time Spent | 24h [ 86400 ] | 24.5h [ 88200 ] |
Worklog Id | 18324 [ 18324 ] |
Status | Local Testing [ 10200 ] | Pending for Stage Approval [ 10300 ] |
Status | Pending for Stage Approval [ 10300 ] | Approved for Stage [ 10030 ] |
Remaining Estimate | 5.5h [ 19800 ] | 3.5h [ 12600 ] |
Time Spent | 24.5h [ 88200 ] | 26.5h [ 95400 ] |
Worklog Id | 18332 [ 18332 ] |
Remaining Estimate | 3.5h [ 12600 ] | 2.5h [ 9000 ] |
Time Spent | 26.5h [ 95400 ] | 27.5h [ 99000 ] |
Worklog Id | 18170 [ 18170 ] |
-
- Time Spent:
- 4h
-
Test case writing and LB testing.
Stage testing
Remaining Estimate | 2.5h [ 9000 ] | 0h [ 0 ] |
Time Spent | 27.5h [ 99000 ] | 31.5h [ 113400 ] |
Worklog Id | 18902 [ 18902 ] |
Time Spent | 31.5h [ 113400 ] | 35h [ 126000 ] |
Worklog Id | 18921 [ 18921 ] |
Time Spent | 35h [ 126000 ] | 36h [ 129600 ] |
Worklog Id | 23146 [ 23146 ] |
Item State | Parent values: Stage QA(10202)Level 1 values: On Hold(10215) | Parent values: Stage QA(10202)Level 1 values: Production Deployment on Hold(10224) |
Status | Approved for Stage [ 10030 ] | Stage Testing [ 10201 ] |
Item State | Parent values: Stage QA(10202)Level 1 values: Production Deployment on Hold(10224) | Parent values: Production Complete(10222)Level 1 values: Closed(10223) |
Status Update | Completed [ 18480 ] |
Status | Stage Testing [ 10201 ] | Pending for Production Approval [ 10301 ] |
Status | Pending for Production Approval [ 10301 ] | Approved for production [ 10034 ] |
Status | Approved for production [ 10034 ] | Production Testing [ 10202 ] |
Resolution | Done [ 10000 ] | |
Status | Production Testing [ 10202 ] | Production Complete [ 10028 ] |
Resolution | Done [ 10000 ] | |
Status | Production Complete [ 10028 ] | Closed [ 6 ] |
Company | LONG Building Technologies [ 13604 ] | New Facility Not Added [ 18435 ] |
Description | Moving tickets for Cancellation | |
Environment | Others [ 18445 ] | |
Issue Type | Enhancement [ 4 ] | Support Activity [ 10301 ] |
Support Task Type | Customization [ 11204 ] | |
Workflow | WT_Features [ 30146 ] | WT_Support [ 63935 ] |
Status | Closed [ 6 ] | Reopen [ 4 ] |
Resolution | Cancelled [ 10300 ] | |
Status | Reopen [ 4 ] | Resolved [ 5 ] |
Transition | Time In Source Status | Execution Times |
---|
|
2d 17h 35m | 1 |
|
5s | 1 |
|
3s | 1 |
|
2s | 1 |
|
9h | 1 |
|
3s | 1 |
|
121d 18h 4m | 1 |
|
278d 21h 27m | 1 |
|
2m 5s | 1 |
|
1m 5s | 1 |
|
2m 41s | 1 |
|
6m 14s | 1 |
|
5h 16m | 1 |
|
2m 11s | 1 |
For column wise paycheck import is getting failed
See below error Log:
ErrorID : 0
ErrorSource : ControllerAppTier.SaveAndGetData->WORKTERRAControllerAppTier.SaveAndGetData->ExecuteImportDTS.ImportData_Isolated->WTIsolatedRoutines.Main->ExecuteImportDTS.ImportData->ImportValidationColumnWise.ImportData->ImportValidationColumnWise.ProcessImportDataFile->ImportValidationColumnWise.GetDataForInsertCheck
ErrorMessage: Incorrect syntax near the keyword 'from'.