shyam sharma
Yes, initial setup of Azure UK instance is done however we listed down set of tasks that needed to be done for production readyness of this environment. I think we should keep this ticket open for those tasks.
1. Reports are not working which need to fix - TBD
2. Decision pending on disaster recovery - 5 days – Disaster could be handle by backup, consider for same region
3. Alert/notification/monitoring services need to configure/test - 2 days
4. How to use share storage device/file server is pending - 1 day
5. Database backup strategy need to finalize - 2 days
6. Machine upgrades (DB/APP/WEB) - 2 days – will move to high configuration
7. Secondary domain controller setup - 1 day
8. Network subnet to be separated for each tier - 1 day
9. Setup Auto scaling mechanism & Path - 3 days
Indraprakash Tiwari
Indraprakash Tiwari Saurabh Sablaka : can you please look in to this and let me know if still you would like to open this ticket ? I mean if POC is done, can you please close this ticket ?