Type:
Enhancement
-
Status: Production Complete
-
Priority:
High
-
Resolution: Done
-
Component/s: BenAdmin
-
Labels:None
-
Module:Platform
-
Reported by:Support
-
Company:Prime Healthcare
-
Item State:Production Complete - Closed
-
Issue Importance:Must Have
We have set up this company on Stage for 'Garden Grove Hospital Medical Center' only. All other data related to employees, election other than Garden Grove are removed from this company.
Please refer attached plan for details.
- relates to
-
ST-64 Splitting out Prime hospitals to their own companies
-
- Closed
-
Field | Original Value | New Value |
---|---|---|
Attachment | Steps to split Prime.docx [ 15498 ] | |
Attachment | Prime Company Admin Mapping.xlsx [ 15499 ] | |
Attachment | Prime Feeds.xlsx [ 15500 ] | |
Attachment | Prime_All Classes.xlsx [ 15501 ] |
Assignee | Hrishikesh Deshpande [ hrishikesh.deshpande ] | Priya Dhamande [ priya.dhamande ] |
Assignee | Priya Dhamande [ priya.dhamande ] | Anirudha Joshi [ anirudha.joshi ] |
Item State | Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602) | Parent values: Stage QA(10202)Level 1 values: In Testing(10214) |
Attachment | Defects_GardenGroveHospitalMedicalCenter_04152016.xls [ 15723 ] |
Attachment | Defects_GardenGroveHospitalMedicalCenter_19April2016.xls [ 15846 ] |
Assignee | Anirudha Joshi [ anirudha.joshi ] | Saurabh Sablaka [ saurabh.sablaka ] |
Attachment | Defects_GardenGroveHospitalMedicalCenter_19April2016.xls [ 15846 ] |
Attachment | Defects_GardenGroveHospitalMedicalCenter_04152016.xls [ 15723 ] |
Attachment | FINALDefects_GardenGroveHospitalMedicalCenter_04152016.xls [ 16300 ] |
Issue Importance | Must Have [ 11800 ] |
Assignee | Saurabh Sablaka [ saurabh.sablaka ] | Jennifer Fernandes [ jjsassy99 ] |
Status | New Request [ 10029 ] | Pending for Approval [ 10002 ] |
Status | Pending for Approval [ 10002 ] | Approved for Development [ 10003 ] |
Status | Approved for Development [ 10003 ] | In Development [ 10007 ] |
Status | In Development [ 10007 ] | Local Testing [ 10200 ] |
Item State | Parent values: Stage QA(10202)Level 1 values: In Testing(10214) | Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602) |
Status | Local Testing [ 10200 ] | Pending for Stage Approval [ 10300 ] |
Status | Pending for Stage Approval [ 10300 ] | Approved for Stage [ 10030 ] |
Status | Approved for Stage [ 10030 ] | Stage Testing [ 10201 ] |
Attachment | UAT Signoff.pdf [ 22840 ] |
Attachment | 2. GardenGroove_Breakout_Plan_05Aug2016.xlsx [ 23267 ] |
Attachment | GGHMC_logo.jpg [ 23268 ] |
Item State | Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602) | Parent values: Production QA(10203)Level 1 values: Production Deployed(10221) |
Attachment | 2. GardenGroove_Breakout_Plan_05Aug2016_completed.xlsx [ 23387 ] |
Status | Stage Testing [ 10201 ] | Pending for Production Approval [ 10301 ] |
Status | Pending for Production Approval [ 10301 ] | Approved for production [ 10034 ] |
Status | Approved for production [ 10034 ] | Production Testing [ 10202 ] |
Attachment | screenshot-1.png [ 24473 ] |
Resolution | Done [ 10000 ] | |
Status | Production Testing [ 10202 ] | Production Complete [ 10028 ] |
Item State | Parent values: Production QA(10203)Level 1 values: Production Deployed(10221) | Parent values: Production Complete(10222)Level 1 values: Closed(10223) |
Transition | Time In Source Status | Execution Times |
---|
|
56d 21h 30m | 1 |
|
2s | 1 |
|
1s | 1 |
|
2s | 1 |
|
12m 50s | 1 |
|
6s | 1 |
|
3s | 1 |
|
60d 22h 56m | 1 |
|
3s | 1 |
|
2s | 1 |
|
10d 20h 21m | 1 |
Hrishikesh Deshpande
Testing in progress on Stage. Will upload the defect sheet once completed.
PFA defects found till today in the sheet 'Defects_GardenGroveHospitalMedicalCenter_04152016.xls'.
Will add to this list as testing progresses.
Regards,
Anirudha Joshi