ACA: Metso | For Loss of Eligibility employees coverage start should be match with event date in offr segement

    Details

    • Type: Change Request
    • Status: Closed
    • Priority: Medium
    • Resolution: Done
    • Affects Version/s: None
    • Fix Version/s: None
    • Component/s: ACA
    • Labels:
    • Environment:
      QA
    • Module:
      ACA
    • Reported by:
      Client
    • Company:
      Metso Benefits
    • Item State:
      Production Complete - Closed
    • Issue Importance:
      Must Have
    • Severity:
      Simple

      Description

      In case of loss of eligibility employee OFFR segment should populate on the file by coverage start date matching with event date.

      Current Implementation : In case of loss of eligibility, employee OFFR segment populates coverage start date as offer date.
      New Implementation : In case of loss of eligibility, employee OFFR segment should populate on the file by coverage start date as event date.

        Attachments

          Issue Links

            Activity

            Transition Time In Source Status Execution Times
            Revansiddha Gaur (Inactive) made transition -
            New Request Pending for Approval
            36s 1
            Revansiddha Gaur (Inactive) made transition -
            Pending for Approval Approved for Development
            3s 1
            Revansiddha Gaur (Inactive) made transition -
            Approved for Development In Development
            16d 21h 41m 1
            Revansiddha Gaur (Inactive) made transition -
            In Development Mockup Approval
            2d 19h 50m 1
            Revansiddha Gaur (Inactive) made transition -
            Mockup Approval Mockup Approved
            1d 22h 51m 1
            Revansiddha Gaur (Inactive) made transition -
            Mockup Approved In Development
            8s 1
            Smita Pawar (Inactive) made transition -
            In Development In LB Testing
            12d 2h 38m 1
            Sachin Hingole (Inactive) made transition -
            In LB Testing Pending for Stage Approval
            21d 23h 43m 1
            Sachin Hingole (Inactive) made transition -
            Pending for Stage Approval Approved for Stage
            2m 38s 1
            Sachin Hingole (Inactive) made transition -
            Approved for Stage Stage Testing
            4m 55s 1
            Smita Pawar (Inactive) made transition -
            Stage Testing Pending for Production Approval
            11d 3h 53m 1
            Smita Pawar (Inactive) made transition -
            Pending for Production Approval Approved for production
            5s 1
            Smita Pawar (Inactive) made transition -
            Approved for production In Production Testing
            3s 1
            Smita Pawar (Inactive) made transition -
            In Production Testing Production Complete
            4d 23m 1
            Smita Pawar (Inactive) made transition -
            Production Complete Closed
            4s 1

              People

              Assignee:
              smita.pawar Smita Pawar (Inactive)
              Reporter:
              revansiddha.gaur Revansiddha Gaur (Inactive)
              Developer:
              Revansiddha Gaur (Inactive)
              QA:
              Smita Pawar (Inactive)
              Votes:
              0 Vote for this issue
              Watchers:
              3 Start watching this issue

                Dates

                Created:
                Updated:
                Resolved:
                Dev Due Date:
                Pre-Prod Due Date:
                Production Due Date:
                Code Review Date:

                  Time Tracking

                  Estimated:
                  Original Estimate - 0h
                  0h
                  Remaining:
                  Remaining Estimate - 0h
                  0h
                  Logged:
                  Time Spent - 21.25h
                  21.25h