Hi,
Per the client:
Can you please assist with some issues on the COST December invoice? Please see the attached pre-bill.
The EHCW fee is showing as $76.63. This is incorrect. The fee should be $41.63.
The EHCW fee for $41.63 is also being credited back for terminated employees. This should not be occurring either. These adjustments should be removed.
The only change that was made to the EHCW fee is the date was extended from 12/31/17 to 12/31/18.- Please see the first attached screen print.
Do I have to add a new rate for 2018?
Then, I extended and recalculated in the SA tool box. The rate is showing as $41.63 in the tool box. Please see second attached screen print.
Thank you,
Kira Hamilton
Debbie Kulling
- relates to
-
NF-5538 City of SeaTac-invoice Issue
-
- Closed
-
Field | Original Value | New Value |
---|---|---|
Module | Parent values: BenAdmin(10100) | Parent values: BenAdmin(10100)Level 1 values: Report(10109) |
Assignee | Satya [ ID10004 ] | Prasanna Karlekar [ prasanna ] |
Assignee | Prasanna Karlekar [ prasanna ] | Jyoti Agrawal [ jyoti.agrawal ] |
Status | Open [ 1 ] | In Progress [ 3 ] |
Assignee | Jyoti Agrawal [ jyoti.agrawal ] | Jyoti Mayne [ jyoti.mayne ] |
Assignee | Jyoti Mayne [ jyoti.mayne ] | Abhilash Warkari [ abhilash.warkari ] |
Issue Type | Support Activity [ 10301 ] | Bug [ 1 ] |
Status | In Progress [ 3 ] | In Development [ 10007 ] |
Support Task Type | Data Correction [ 11203 ] | |
Workflow | WT_Support [ 57994 ] | WT_Defects [ 58060 ] |
-
- Time Spent:
- 8h
-
-Issue analysis
-discussion with Prasanna and Jyoti mayne
-code fix
-unit testing
-verification in production
-Jira update
Remaining Estimate | 0h [ 0 ] | |
Time Spent | 8h [ 28800 ] | |
Worklog Id | 91669 [ 91669 ] |
Time Spent | 8h [ 28800 ] | 9h [ 32400 ] |
Worklog Id | 91677 [ 91677 ] |
-
- Time Spent:
- 1.5h
-
Analysis of the issue.
Data analysis.
Performed Scenario.
Discussion with jyoti
Item State | Parent values: Development(10200)Level 1 values: In Analysis(10204) | |
Original Estimate | 0h [ 0 ] |
-
- Time Spent:
- 1h
-
Issue discussion - Trigger and Procedure
Discussion with Enrollment team
Discussion on fix to be done
Review of reply to be done
Approval status | Need approval for development [ 18452 ] |
Assignee | Abhilash Warkari [ abhilash.warkari ] | Jyoti Mayne [ jyoti.mayne ] |
Attachment | MARGARITA FLORES History.PNG [ 68223 ] |
Assignee | Jyoti Mayne [ jyoti.mayne ] | Jyoti Agrawal [ jyoti.agrawal ] |
Dev Due Date | 24/Nov/2017 | |
Dev Estimates | 25 |
-
- Time Spent:
- 1.5h
-
Data correction
Invoice verification
Jira update
Analysis on Issue 1
Time Spent | 9h [ 32400 ] | 10.5h [ 37800 ] |
Worklog Id | 91920 [ 91920 ] |
-
- Time Spent:
- 1.5h
-
scenario discussion with Report team
data correction ans its verification
Item State | Parent values: Development(10200)Level 1 values: In Analysis(10204) | Parent values: Development(10200)Level 1 values: In Progress(10206) |
-
- Time Spent:
- 5.5h
-
Code fix, unit testing, script creation, scanning of affected companies
Time Spent | 10.5h [ 37800 ] | 17h [ 61200 ] |
Worklog Id | 92143 [ 92143 ] |
Remaining Estimate | 0h [ 0 ] | 1h [ 3600 ] |
Time Spent | 17h [ 61200 ] | 16h [ 57600 ] |
Worklog Id | 92143 [ 92143 ] |
Remaining Estimate | 1h [ 3600 ] | 0h [ 0 ] |
Time Spent | 16h [ 57600 ] | 17.5h [ 63000 ] |
Worklog Id | 92167 [ 92167 ] |
-
- Time Spent:
- 4h
-
Unit testing, data verification on prod companies
Time Spent | 17.5h [ 63000 ] | 21.5h [ 77400 ] |
Worklog Id | 92387 [ 92387 ] |
Time Spent | 21.5h [ 77400 ] | 23h [ 82800 ] |
Worklog Id | 92590 [ 92590 ] |
Item State | Parent values: Development(10200)Level 1 values: In Progress(10206) | Parent values: Development(10200) |
Item State | Parent values: Development(10200) | Parent values: Development(10200)Level 1 values: In Analysis(10204) |
Dev Due Date | 24/Nov/2017 | 27/Nov/2017 |
Time Spent | 23h [ 82800 ] | 24h [ 86400 ] |
Worklog Id | 92778 [ 92778 ] |
-
- Time Spent:
- 1h
-
Code review
Data correction and scanning script review
Scenario discussion
-
- Time Spent:
- 2h
-
Data scan script writing, data scanning in all companies, data correction
Time Spent | 24h [ 86400 ] | 26h [ 93600 ] |
Worklog Id | 92990 [ 92990 ] |
Sprint | WT Sprint 41 - Bugs [ 95 ] |
Labels | invoice_management |
Sprint | WT Sprint 41 - Bugs [ 95 ] |
Sprint | WT Sprint 41 - Bugs [ 95 ] |
Dev Due Date | 27/Nov/2017 | 13/Dec/2017 |
Dev Estimates | 25 | 30 |
Item State | Parent values: Development(10200)Level 1 values: In Analysis(10204) | Parent values: Development(10200)Level 1 values: Ready for Local Testing(10209) |
QA | Venkatesh Pujari [ venkatesh.pujari ] | |
QA Estimates | 6 |
Approval status | Need approval for development [ 18452 ] | Approved for development [ 18453 ] |
Development Approval | Yes [ 18474 ] |
Stage Due Date | 22/Dec/17 [ 2017-12-22 ] |
Item State | Parent values: Development(10200)Level 1 values: Ready for Local Testing(10209) | Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) |
Attachment | Invoice_Management_WT-12216.xls [ 69859 ] |
-
- Time Spent:
- 2.5h
-
Analysis and test scenarios
Time Spent | 26h [ 93600 ] | 28.5h [ 102600 ] |
Worklog Id | 95732 [ 95732 ] |
Attachment | FW 1211 Sprint - Development Approval.msg [ 69875 ] |
Status | In Development [ 10007 ] | Local Testing [ 10200 ] |
Assignee | Jyoti Agrawal [ jyoti.agrawal ] | Venkatesh Pujari [ venkatesh.pujari ] |
Root Cause | Scenario/Requirement Missed [ 18432 ] |
Item State | Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) | Parent values: LB QA(10201)Level 1 values: In Testing(10210) |
Item State | Parent values: LB QA(10201)Level 1 values: In Testing(10210) | Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213) |
Time Spent | 28.5h [ 102600 ] | 30.5h [ 109800 ] |
Worklog Id | 95892 [ 95892 ] |
Item State | Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213) | Parent values: LB QA(10201)Level 1 values: In Testing(10210) |
Attachment |
Invoice_Management_ |
Attachment | Invoice_Management_WT-12216.xls [ 69974 ] |
-
- Time Spent:
- 1.5h
-
Testing of additional scenarios
Item State | Parent values: LB QA(10201)Level 1 values: In Testing(10210) | Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213) |
Time Spent | 30.5h [ 109800 ] | 32h [ 115200 ] |
Worklog Id | 95930 [ 95930 ] |
-
- Time Spent:
- 0.75h
-
JIRA update
Email communication
Item State | Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213) | Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602) |
Deployment Approval | Approved for stage deployment [ 18455 ] | |
Production Due Date | 29/Dec/2017 |
Status | Local Testing [ 10200 ] | Stage Testing [ 10201 ] |
Item State | Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602) | Parent values: Stage QA(10202)Level 1 values: In Testing(10214) |
Item State | Parent values: Stage QA(10202)Level 1 values: In Testing(10214) | Parent values: Stage QA(10202)Level 1 values: Ready for Production(10217) |
Time Spent | 32h [ 115200 ] | 36h [ 129600 ] |
Worklog Id | 98243 [ 98243 ] |
Item State | Parent values: Stage QA(10202)Level 1 values: Ready for Production(10217) | Parent values: Production QA(10203)Level 1 values: Production Deployed(10221) |
Comments |
Hi All, Following point has been approved for production deployment on 12/29 Regards Gaurav |
|
Deployment Approval | Approved for stage deployment [ 18455 ] | Approved for production deployment [ 18457 ] |
Status | Stage Testing [ 10201 ] | Production Testing [ 10202 ] |
Item State | Parent values: Production QA(10203)Level 1 values: Production Deployed(10221) | Parent values: Production QA(10203)Level 1 values: In Testing(10218) |
Item State | Parent values: Production QA(10203)Level 1 values: In Testing(10218) | Parent values: Production Complete(10222) |
Item State | Parent values: Production Complete(10222) | Parent values: Production Complete(10222)Level 1 values: Closed(10223) |
Assignee | Venkatesh Pujari [ venkatesh.pujari ] | Kira Hamilton [ kira.hamilton ] |
Resolution | Fixed [ 1 ] | |
Status | Production Testing [ 10202 ] | Production Complete [ 10028 ] |
Time Spent | 36h [ 129600 ] | 38h [ 136800 ] |
Worklog Id | 98622 [ 98622 ] |
Time Spent | 38h [ 136800 ] | 38.75h [ 139500 ] |
Worklog Id | 99084 [ 99084 ] |
Transition | Time In Source Status | Execution Times |
---|
|
2d 12h 52m | 1 |
|
3h 38m | 1 |
|
21d 23h 16m | 1 |
|
14d 17h 9m | 1 |
|
2d 52m | 1 |
|
2h 19m | 1 |
Hi Kira Hamilton,
Below are updates :-
Issue 1(The EHCW fee is showing as $76.63):
This is a script issue. Invoice is considering current as well as extended rate.
We will be creating new bug ticket to give fix for this.
For now we have done script correction in City of SeaTac. Please regenerate December invoice to get correct cost $41.63.
Issue 2 (The EHCW fee for $41.63 is also being credited back for terminated employees):
As per data in tables invoice is pulling correct adjustments. For employees getting adjustments, rate 'EHCW 2017/2018' was active from 4/1/2017 and has been termed as never effective by '3/31/17'. Hence, adjustments are appearing back from April.
We will ask enrollment team to look into this
Hi Jyoti Mayne, could you please check Issue 2.
Thanks,
Jyoti Agrawal
cc:Prasanna Karlekar,Gaurav Sodani