Type:
Enhancement
-
Status: Production Complete
-
Priority:
Medium
-
Resolution: Done
-
Affects Version/s: None
-
Fix Version/s: None
-
Component/s: ACA
-
Labels:None
-
Module:ACA
-
Reported by:Harbinger
-
Item State:Production Complete - Closed
-
Issue Importance:Good To Have
Concern : Address/city etc length is greater than max length come to know on verifying a submission
Cause : As per IRS XSD Constraint
Correction : Need to give the list of such issues with employee details to correct before verifying a submission.
Need to give the discrepancy report in below times...
1. While 1095 c report run finalization time
2. On IRS xml submission files, Verify Submission -generating xml files.
Estimation in days
Hi Nandkumar Prabhakar Karlekar,
Please approve this jira.
Regards,
Revan