Type:
Enhancement
-
Status: Production Complete
-
Priority:
Medium
-
Resolution: Done
-
Affects Version/s: None
-
Fix Version/s: None
-
Component/s: ACA
-
Labels:None
-
Module:ACA
-
Reported by:Harbinger
-
Item State:Production Complete - Closed
-
Issue Importance:Good To Have
Concern : Address/city etc length is greater than max length come to know on verifying a submission
Cause : As per IRS XSD Constraint
Correction : Need to give the list of such issues with employee details to correct before verifying a submission.
Need to give the discrepancy report in below times...
1. While 1095 c report run finalization time
2. On IRS xml submission files, Verify Submission -generating xml files.
Estimation in days
Field | Original Value | New Value |
---|---|---|
Status | New Request [ 10029 ] | Pending for Approval [ 10002 ] |
Assignee | Nandkumar [ satyap ] | Revansiddha Gaur [ revansiddha.gaur ] |
Status | Pending for Approval [ 10002 ] | Approved for Development [ 10003 ] |
Description |
Concern : Address/city etc length is greater than max length come to know on verifying a submission Cause : As per IRS XSD Constraint Correction : Need to give the list of such issues with employee details to correct before verifying a submission. *Estimation in days* |
Concern : Address/city etc length is greater than max length come to know on verifying a submission Cause : As per IRS XSD Constraint Correction : Need to give the list of such issues with employee details to correct before verifying a submission. *Estimation in days* |
Item State | Parent values: Development(10200)Level 1 values: On Hold(10207) |
Description |
Concern : Address/city etc length is greater than max length come to know on verifying a submission Cause : As per IRS XSD Constraint Correction : Need to give the list of such issues with employee details to correct before verifying a submission. *Estimation in days* |
Concern : Address/city etc length is greater than max length come to know on verifying a submission Cause : As per IRS XSD Constraint Correction : Need to give the list of such issues with employee details to correct before verifying a submission. Need to give the discrepancy report in below times... 1. While 1095 c report run finalization time 2. On IRS xml submission files, Verify Submission -generating xml files. *Estimation in days* |
Assignee | Revansiddha Gaur [ revansiddha.gaur ] | Kumar Chhajed [ kumar.chhajed ] |
Remaining Estimate | 70h [ 252000 ] | |
Original Estimate | 70h [ 252000 ] |
Status | Approved for Development [ 10003 ] | In Development [ 10007 ] |
Item State | Parent values: Development(10200)Level 1 values: On Hold(10207) | Parent values: Development(10200)Level 1 values: In Analysis(10204) |
Developer | Kumar Chhajed [ kumar.chhajed ] | |
QA | Sachin Hingole [ sachin.hingole ] |
-
- Time Spent:
- 1h
-
Coding - Writing SP and DDL
Unit testing
Remaining Estimate | 70h [ 252000 ] | 69h [ 248400 ] |
Time Spent | 1h [ 3600 ] | |
Worklog Id | 10409 [ 10409 ] |
Remaining Estimate | 69h [ 248400 ] | 68h [ 244800 ] |
Time Spent | 1h [ 3600 ] | 2h [ 7200 ] |
Worklog Id | 10449 [ 10449 ] |
Item State | Parent values: Development(10200)Level 1 values: In Analysis(10204) | Parent values: Development(10200)Level 1 values: In Progress(10206) |
-
- Time Spent:
- 1h
-
discussion of the format and review of UI
Remaining Estimate | 68h [ 244800 ] | 67h [ 241200 ] |
Time Spent | 2h [ 7200 ] | 3h [ 10800 ] |
Worklog Id | 10520 [ 10520 ] |
Remaining Estimate | 67h [ 241200 ] | 59h [ 212400 ] |
Time Spent | 3h [ 10800 ] | 11h [ 39600 ] |
Worklog Id | 10527 [ 10527 ] |
-
- Time Spent:
- 20m
-
Discussion on XSD Validation failed reason.
Remaining Estimate | 59h [ 212400 ] | 58h 40m [ 211200 ] |
Time Spent | 11h [ 39600 ] | 11h 20m [ 40800 ] |
Worklog Id | 10608 [ 10608 ] |
Remaining Estimate | 58h 40m [ 211200 ] | 53h 10m [ 191400 ] |
Time Spent | 11h 20m [ 40800 ] | 16h 50m [ 60600 ] |
Worklog Id | 10614 [ 10614 ] |
-
- Time Spent:
- 8h
-
Analysis and Test case writing
Remaining Estimate | 53h 10m [ 191400 ] | 45h 10m [ 162600 ] |
Time Spent | 16h 50m [ 60600 ] | 24h 50m [ 89400 ] |
Worklog Id | 10722 [ 10722 ] |
Worklog Id | 10722 [ 10722 ] |
Remaining Estimate | 45h 10m [ 162600 ] | 40h 40m [ 146400 ] |
Time Spent | 24h 50m [ 89400 ] | 29h 20m [ 105600 ] |
Worklog Id | 10764 [ 10764 ] |
-
- Time Spent:
- 4.5h
-
Coding, Internal discussion and unit testing
Remaining Estimate | 40h 40m [ 146400 ] | 36h 10m [ 130200 ] |
Time Spent | 29h 20m [ 105600 ] | 33h 50m [ 121800 ] |
Worklog Id | 10980 [ 10980 ] |
-
- Time Spent:
- 20m
-
Internal Discussion for Discrepancy Report Review
Remaining Estimate | 36h 10m [ 130200 ] | 35h 50m [ 129000 ] |
Time Spent | 33h 50m [ 121800 ] | 34h 10m [ 123000 ] |
Worklog Id | 11048 [ 11048 ] |
-
- Time Spent:
- 6h
-
Coding,Unit testing, Internal discussion
Remaining Estimate | 35h 50m [ 129000 ] | 29h 50m [ 107400 ] |
Time Spent | 34h 10m [ 123000 ] | 40h 10m [ 144600 ] |
Worklog Id | 11172 [ 11172 ] |
Worklog Id | 11048 [ 11048 ] |
Item State | Parent values: Development(10200)Level 1 values: In Progress(10206) | Parent values: Development(10200)Level 1 values: Ready for Review(10208) |
Remaining Estimate | 29h 50m [ 107400 ] | 4h 50m [ 17400 ] |
Original Estimate | 70h [ 252000 ] | 45h [ 162000 ] |
-
- Time Spent:
- 4.5h
-
Coding
Unit Testing
Code Review
LB and Trunk Check-ins
Remaining Estimate | 4h 50m [ 17400 ] | 20m [ 1200 ] |
Time Spent | 40h 10m [ 144600 ] | 44h 40m [ 160800 ] |
Worklog Id | 11315 [ 11315 ] |
Code Review Date | 02/Dec/2016 | |
Code Reviewed By | Ramya Tantry [ 13001 ] |
Item State | Parent values: Development(10200)Level 1 values: Ready for Review(10208) | Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) |
Assignee | Kumar Chhajed [ kumar.chhajed ] | Sachin Hingole [ sachin.hingole ] |
Remaining Estimate | 20m [ 1200 ] | 0h [ 0 ] |
Time Spent | 44h 40m [ 160800 ] | 45h [ 162000 ] |
Worklog Id | 11407 [ 11407 ] |
Status | In Development [ 10007 ] | Local Testing [ 10200 ] |
Item State | Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) | Parent values: LB QA(10201)Level 1 values: In Testing(10210) |
Remaining Estimate | 0h [ 0 ] | 35h [ 126000 ] |
Original Estimate | 45h [ 162000 ] | 80h [ 288000 ] |
Worklog Id | 11407 [ 11407 ] |
Assignee | Sachin Hingole [ sachin.hingole ] | Mahendra Mungase [ mahendra.mungase ] |
-
- Time Spent:
- 8h
-
Testing of Enhancement on LB
Remaining Estimate | 35h [ 126000 ] | 27h [ 97200 ] |
Time Spent | 45h [ 162000 ] | 53h [ 190800 ] |
Worklog Id | 12137 [ 12137 ] |
Attachment | Test_Case_WT_2719.xls [ 34714 ] |
Item State | Parent values: LB QA(10201)Level 1 values: In Testing(10210) | Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213) |
Item State | Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213) | Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602) |
Status | Local Testing [ 10200 ] | Pending for Stage Approval [ 10300 ] |
Status | Pending for Stage Approval [ 10300 ] | Approved for Stage [ 10030 ] |
Status | Approved for Stage [ 10030 ] | Stage Testing [ 10201 ] |
Item State | Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602) | Parent values: Stage QA(10202)Level 1 values: In Testing(10214) |
Item State | Parent values: Stage QA(10202)Level 1 values: In Testing(10214) | Parent values: Stage QA(10202)Level 1 values: Ready for Production(10217) |
-
- Time Spent:
- 3.5h
-
Stage testing
Remaining Estimate | 27h [ 97200 ] | 24h [ 86400 ] |
Time Spent | 53h [ 190800 ] | 56h [ 201600 ] |
Worklog Id | 12514 [ 12514 ] |
Remaining Estimate | 24h [ 86400 ] | 23.5h [ 84600 ] |
Time Spent | 56h [ 201600 ] | 56.5h [ 203400 ] |
Worklog Id | 12514 [ 12514 ] |
-
- Time Spent:
- 0.5h
-
Stage check-ins
Internal discussion with Mahendra
Remaining Estimate | 23.5h [ 84600 ] | 23h [ 82800 ] |
Time Spent | 56.5h [ 203400 ] | 57h [ 205200 ] |
Worklog Id | 12576 [ 12576 ] |
Item State | Parent values: Stage QA(10202)Level 1 values: Ready for Production(10217) | Parent values: Production QA(10203)Level 1 values: Production Deployed(10221) |
Remaining Estimate | 23h [ 82800 ] | 20h [ 72000 ] |
Time Spent | 57h [ 205200 ] | 60h [ 216000 ] |
Worklog Id | 12776 [ 12776 ] |
Item State | Parent values: Production QA(10203)Level 1 values: Production Deployed(10221) | Parent values: Production QA(10203)Level 1 values: In Testing(10218) |
Status | Stage Testing [ 10201 ] | Pending for Production Approval [ 10301 ] |
Status | Pending for Production Approval [ 10301 ] | Approved for production [ 10034 ] |
Status | Approved for production [ 10034 ] | Production Testing [ 10202 ] |
Remaining Estimate | 20h [ 72000 ] | 17h [ 61200 ] |
Time Spent | 60h [ 216000 ] | 63h [ 226800 ] |
Worklog Id | 17892 [ 17892 ] |
Item State | Parent values: Production QA(10203)Level 1 values: In Testing(10218) | Parent values: Production QA(10203)Level 1 values: On Hold(10219) |
Resolution | Fixed [ 1 ] | |
Status | Production Testing [ 10202 ] | Production Complete [ 10028 ] |
Item State | Parent values: Production QA(10203)Level 1 values: On Hold(10219) | Parent values: Production Complete(10222)Level 1 values: Closed(10223) |
Transition | Time In Source Status | Execution Times |
---|
|
8d 6h 44m | 1 |
|
32s | 1 |
|
172d 18h 19m | 1 |
|
12d 2h 52m | 1 |
|
6d 22h 38m | 1 |
|
3s | 1 |
|
2s | 1 |
|
1d 4h 44m | 1 |
|
3s | 1 |
|
3s | 1 |
|
44d 15h 37m | 1 |
Hi Nandkumar Prabhakar Karlekar,
Please approve this jira.
Regards,
Revan