Uploaded image for project: 'WORKTERRA'
  1. WORKTERRA
  2. WT-4337

Export > Able to set future date while inserting base run date for a template

    Details

    • Type: Bug
    • Status: Closed
    • Priority: Medium
    • Resolution: Done
    • Affects Version/s: None
    • Fix Version/s: None
    • Component/s: BenAdmin
    • Labels:
      None
    • Environment:
      Stage
    • Module:
      BenAdmin - Export
    • Reported by:
      Harbinger
    • Item State:
      Production Complete - Closed
    • Issue Importance:
      Must Have

      Description

      Steps to Reproduce

      1) Click in the Set Run Date/Time field
      2) Click on Right arrow to Traverse few months ahead
      3) Select specific time
      4) Select checkbox next to Template name
      4) Click on Set Run Date/Time button

      Result : Future Run date get set for the template (PFA Screenshot)

        Attachments

          Activity

          aniruddha.dev Aniruddha Dev (Inactive) created issue -
          aniruddha.dev Aniruddha Dev (Inactive) made changes -
          Field Original Value New Value
          Environment Stage [ 10004 ]
          aniruddha.dev Aniruddha Dev (Inactive) made changes -
          Attachment Add Run Date_issue.JPG [ 24837 ]
          aniruddha.dev Aniruddha Dev (Inactive) made changes -
          Description Steps to Reproduce

          1) Click in the Set Run Date/Time field
          2) Click on Right arrow to Traverse few months ahead
          3) Select specific time
          4) Select checkbox next to Template name
          4) Click on Set Run Date/Time button

          Result : Future Run date get set for the template
          Steps to Reproduce

          1) Click in the Set Run Date/Time field
          2) Click on Right arrow to Traverse few months ahead
          3) Select specific time
          4) Select checkbox next to Template name
          4) Click on Set Run Date/Time button

          Result : Future Run date get set for the template (PFA Screenshot)
          rakeshr Rakesh Roy (Inactive) made changes -
          Issue Importance Must Have [ 11800 ]
          Hide
          rohan.khandave Rohan J Khandave (Inactive) added a comment -

          Affected Files :

          Web Server

          1. EDITool.cshtml
          2. WORKTERRAShared.js

          Show
          rohan.khandave Rohan J Khandave (Inactive) added a comment - Affected Files : Web Server 1. EDITool.cshtml 2. WORKTERRAShared.js
          rohan.khandave Rohan J Khandave (Inactive) made changes -
          Status Open [ 1 ] In Development [ 10007 ]
          rohan.khandave Rohan J Khandave (Inactive) made changes -
          Item State Parent values: Development(10200)Level 1 values: In Progress(10206)
          rohan.khandave Rohan J Khandave (Inactive) made changes -
          Developer Rohan Khandave [ rohan.khandave ]
          rohan.khandave Rohan J Khandave (Inactive) made changes -
          Code Reviewed By Ganesh Sadawarte [ 12101 ]
          rohan.khandave Rohan J Khandave (Inactive) made changes -
          Item State Parent values: Development(10200)Level 1 values: In Progress(10206) Parent values: Development(10200)Level 1 values: Ready for Local Testing(10209)
          rohan.khandave Rohan J Khandave (Inactive) made changes -
          Status In Development [ 10007 ] Local Testing [ 10200 ]
          Hide
          rohan.khandave Rohan J Khandave (Inactive) added a comment -

          Hello Aniruddha Dev,

          Please check after LB deployment.

          Thanks,
          RohanK

          CC – Vinayak Kulkarni , Ganesh Sadawarte

          Show
          rohan.khandave Rohan J Khandave (Inactive) added a comment - Hello Aniruddha Dev , Please check after LB deployment. Thanks, RohanK CC – Vinayak Kulkarni , Ganesh Sadawarte
          rohan.khandave Rohan J Khandave (Inactive) made changes -
          Assignee Rohan Khandave [ rohan.khandave ] Aniruddha Dev [ aniruddha.dev ]
          Hide
          rohan.khandave Rohan J Khandave (Inactive) added a comment -

          3C's

          Concern : User can select date grater than today's date.

          Cause : There one issue in calendar where it doesn't consider max and min time.

          Correction : We have done necessary changes into Calendar control.

          Aniruddha Dev please verify import export delivery screen for impact testing as same calendar control is used on same page.

          Show
          rohan.khandave Rohan J Khandave (Inactive) added a comment - 3C's Concern : User can select date grater than today's date. Cause : There one issue in calendar where it doesn't consider max and min time. Correction : We have done necessary changes into Calendar control. Aniruddha Dev please verify import export delivery screen for impact testing as same calendar control is used on same page.
          gokul.sonawane Gokul Sonawane (Inactive) made changes -
          Item State Parent values: Development(10200)Level 1 values: Ready for Local Testing(10209) Parent values: LB QA(10201)Level 1 values: LB Deployed(11600)
          hrishikesh.deshpande Hrishikesh Deshpande (Inactive) made changes -
          Assignee Aniruddha Dev [ aniruddha.dev ] Priya Dhamande [ priya.dhamande ]
          priya.dhamande Priya Dhamande (Inactive) made changes -
          Item State Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) Parent values: LB QA(10201)Level 1 values: In Testing(10210)
          Hide
          priya.dhamande Priya Dhamande (Inactive) added a comment -

          The issue is verified on LB for Able to set future date while inserting base run date, it is working as expected.

          Scenarios covered.
          1. Checking for Individual template
          2. Checking for Group Template

          Checking template delivery page of Templates for Daily, Weekly, OnTime, Monthly, Week day and Calendar Dates for both Individual template and group template.

          Impact testing: The file for Template delivery is only checked by opening the calendar and setting the date. The file is exported or not through schedule is not checked as it is on lb. Will verify it on stage.

          This is ready for stage.

          Show
          priya.dhamande Priya Dhamande (Inactive) added a comment - The issue is verified on LB for Able to set future date while inserting base run date, it is working as expected. Scenarios covered. 1. Checking for Individual template 2. Checking for Group Template Checking template delivery page of Templates for Daily, Weekly, OnTime, Monthly, Week day and Calendar Dates for both Individual template and group template. Impact testing: The file for Template delivery is only checked by opening the calendar and setting the date. The file is exported or not through schedule is not checked as it is on lb. Will verify it on stage. This is ready for stage.
          priya.dhamande Priya Dhamande (Inactive) made changes -
          Item State Parent values: LB QA(10201)Level 1 values: In Testing(10210) Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213)
          gokul.sonawane Gokul Sonawane (Inactive) made changes -
          Item State Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213) Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602)
          Hide
          priya.dhamande Priya Dhamande (Inactive) added a comment -

          The issue is verified on ASML for HSpl on Stage for the issue Able to set future date while inserting base run date, it is working as expected.
          Scenarios covered.

          1. Checking for Individual template
          2. Checking for Group Template

          Checking template delivery page of Templates only on Weekly, for Individual template template.

          Impact testing: The file for Template delivery is only checked by opening the calendar and setting the date. Also, checked file through ftp delivery mode.

          This is ready for production.

          Show
          priya.dhamande Priya Dhamande (Inactive) added a comment - The issue is verified on ASML for HSpl on Stage for the issue Able to set future date while inserting base run date, it is working as expected. Scenarios covered. 1. Checking for Individual template 2. Checking for Group Template Checking template delivery page of Templates only on Weekly, for Individual template template. Impact testing: The file for Template delivery is only checked by opening the calendar and setting the date. Also, checked file through ftp delivery mode. This is ready for production.
          priya.dhamande Priya Dhamande (Inactive) made changes -
          Status Local Testing [ 10200 ] Stage Testing [ 10201 ]
          priya.dhamande Priya Dhamande (Inactive) made changes -
          Item State Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602) Parent values: Stage QA(10202)Level 1 values: Ready for Production(10217)
          satyap Satya made changes -
          Item State Parent values: Stage QA(10202)Level 1 values: Ready for Production(10217) Parent values: Production QA(10203)Level 1 values: Production Deployed(10221)
          priya.dhamande Priya Dhamande (Inactive) made changes -
          Assignee Priya Dhamande [ priya.dhamande ] Aniruddha Dev [ aniruddha.dev ]
          aniruddha.dev Aniruddha Dev (Inactive) made changes -
          Status Stage Testing [ 10201 ] Production Testing [ 10202 ]
          aniruddha.dev Aniruddha Dev (Inactive) made changes -
          Item State Parent values: Production QA(10203)Level 1 values: Production Deployed(10221) Parent values: Production QA(10203)Level 1 values: In Testing(10218)
          Hide
          aniruddha.dev Aniruddha Dev (Inactive) added a comment -

          Verified the fix on Production . Working as expected

          Show
          aniruddha.dev Aniruddha Dev (Inactive) added a comment - Verified the fix on Production . Working as expected
          aniruddha.dev Aniruddha Dev (Inactive) made changes -
          Resolution Fixed [ 1 ]
          Status Production Testing [ 10202 ] Production Complete [ 10028 ]
          aniruddha.dev Aniruddha Dev (Inactive) made changes -
          Item State Parent values: Production QA(10203)Level 1 values: In Testing(10218) Parent values: Production Complete(10222)Level 1 values: Closed(10223)
          aniruddha.dev Aniruddha Dev (Inactive) made changes -
          Status Production Complete [ 10028 ] Closed [ 6 ]
          hrishikesh.deshpande Hrishikesh Deshpande (Inactive) made changes -
          Assignee Aniruddha Dev [ aniruddha.dev ] Hrishikesh Deshpande [ hrishikesh.deshpande ]
          satyap Satya made changes -
          Environment_New Stage [ 18443 ]
          Transition Time In Source Status Execution Times
          Rohan J Khandave (Inactive) made transition -
          Open In Development
          1d 17h 16m 1
          Rohan J Khandave (Inactive) made transition -
          In Development In LB Testing
          3m 5s 1
          Priya Dhamande (Inactive) made transition -
          In LB Testing Stage Testing
          4d 6h 20m 1
          Aniruddha Dev (Inactive) made transition -
          Stage Testing In Production Testing
          8d 39m 1
          Aniruddha Dev (Inactive) made transition -
          In Production Testing Production Complete
          26s 1
          Aniruddha Dev (Inactive) made transition -
          Production Complete Closed
          13s 1

            People

            Assignee:
            hrishikesh.deshpande Hrishikesh Deshpande (Inactive)
            Reporter:
            aniruddha.dev Aniruddha Dev (Inactive)
            Developer:
            Rohan J Khandave (Inactive)
            QA:
            Aniruddha Dev (Inactive)
            Votes:
            0 Vote for this issue
            Watchers:
            3 Start watching this issue

              Dates

              Created:
              Updated:
              Resolved: