Uploaded image for project: 'WORKTERRA'
  1. WORKTERRA
  2. WT-6569

WT -> BCC Invoice Enhancement -> Few remaining textual changes

    Details

    • Type: Change Request
    • Status: Closed
    • Priority: Medium
    • Resolution: Done
    • Affects Version/s: None
    • Fix Version/s: None
    • Component/s: BenAdmin
    • Labels:
      None
    • Module:
      BenAdmin - Report
    • Reported by:
      Harbinger
    • Item State:
      Production Complete - Closed
    • Sprint:
      WT Sprint 17

      Description

      please refer the screenshot

      CC - Rakesh Roy Deepali Tidke

        Attachments

          Issue Links

            Activity

            alankar.chavan Alankar Chavan (Inactive) created issue -
            alankar.chavan Alankar Chavan (Inactive) made changes -
            Field Original Value New Value
            Link This issue relates to WT-3862 [ WT-3862 ]
            vijays Vijay Siddha (Inactive) made changes -
            Assignee Vijay Siddha [ vijays ] Shyam Sharma [ shyam sharma ]
            alankar.chavan Alankar Chavan (Inactive) made changes -
            Assignee Shyam Sharma [ shyam sharma ] Prasanna Karlekar [ prasanna ]
            shyam.sharma shyam sharma (Inactive) made changes -
            Description
            please refer the screenshot

            CC - [~rakeshr] [~deepalit]

            please refer the screenshot

            CC - [~rakeshr] [~deepalit]

            Sprint WT Sprint 17 [ 32 ]
            prasanna Prasanna Karlekar (Inactive) made changes -
            Code Review Date 28/Nov/2016
            Code Reviewed By Prasanna Karlekar [ 11907 ]
            Dev Due Date 28/Nov/2016
            Dev Estimates 2.5
            prasanna Prasanna Karlekar (Inactive) made changes -
            Assignee Prasanna Karlekar [ prasanna ] Surender Kumar [ surender.kumar ]
            prasanna Prasanna Karlekar (Inactive) made changes -
            Assignee Surender Kumar [ surender.kumar ] Prasanna Karlekar [ prasanna ]
            Developer Surender Kumar [ surender.kumar ]
            surender.kumar surender kumar (Inactive) logged work - 25/Nov/16 01:47 PM
            • Time Spent:
              0.5h
               
              • Analysis
              • Fix issue
            khandu.kshirsagar Khandu Kshirsagar (Inactive) made changes -
            Item State Parent values: LB QA(10201)Level 1 values: LB Deployed(11600)
            surender.kumar surender kumar (Inactive) made changes -
            Assignee Prasanna Karlekar [ prasanna ] Alankar Chavan [ alankar.chavan ]
            alankar.chavan Alankar Chavan (Inactive) made changes -
            Remaining Estimate 1h [ 3600 ]
            Original Estimate 1h [ 3600 ]
            Hide
            alankar.chavan Alankar Chavan (Inactive) added a comment - - edited

            Tested on WT Stage - 30th Nov 2016
            Working well

            Changes are made as per the suggestion given in attached screen shot

            Ready for Stage

            CC - Deepali Tidke Rakesh Roy

            Show
            alankar.chavan Alankar Chavan (Inactive) added a comment - - edited Tested on WT Stage - 30th Nov 2016 Working well Changes are made as per the suggestion given in attached screen shot Ready for Stage CC - Deepali Tidke Rakesh Roy
            alankar.chavan Alankar Chavan (Inactive) made changes -
            Remaining Estimate 1h [ 3600 ] 0.5h [ 1800 ]
            Time Spent 0.5h [ 1800 ]
            Worklog Id 10793 [ 10793 ]
            alankar.chavan Alankar Chavan (Inactive) made changes -
            Item State Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213)
            alankar.chavan Alankar Chavan (Inactive) logged work - 01/Dec/16 06:05 AM
            • Time Spent:
              0.5h
               
              <No comment>
            shyam.sharma shyam sharma (Inactive) made changes -
            Status New Request [ 10029 ] Pending for Approval [ 10002 ]
            shyam.sharma shyam sharma (Inactive) made changes -
            Status Pending for Approval [ 10002 ] Approved for Development [ 10003 ]
            shyam.sharma shyam sharma (Inactive) made changes -
            Status Approved for Development [ 10003 ] In Development [ 10007 ]
            shyam.sharma shyam sharma (Inactive) made changes -
            Status In Development [ 10007 ] Local Testing [ 10200 ]
            shyam.sharma shyam sharma (Inactive) made changes -
            Status Local Testing [ 10200 ] Pending for Stage Approval [ 10300 ]
            surender.kumar surender kumar (Inactive) made changes -
            Remaining Estimate 0.5h [ 1800 ] 0h [ 0 ]
            Time Spent 0.5h [ 1800 ] 1h [ 3600 ]
            Worklog Id 11349 [ 11349 ]
            khandu.kshirsagar Khandu Kshirsagar (Inactive) made changes -
            Item State Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213) Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602)
            alankar.chavan Alankar Chavan (Inactive) made changes -
            Item State Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602) Parent values: Stage QA(10202)Level 1 values: On Hold(10215)
            Hide
            alankar.chavan Alankar Chavan (Inactive) added a comment -

            Tested on Stage - Ready for Production
            keeping this on HOLD as we will move these items on Production with main enhancement (which is at Stage currently)

            Show
            alankar.chavan Alankar Chavan (Inactive) added a comment - Tested on Stage - Ready for Production keeping this on HOLD as we will move these items on Production with main enhancement (which is at Stage currently)
            rakeshr Rakesh Roy (Inactive) made changes -
            Status Pending for Stage Approval [ 10300 ] Approved for Stage [ 10030 ]
            rakeshr Rakesh Roy (Inactive) made changes -
            Status Approved for Stage [ 10030 ] Stage Testing [ 10201 ]
            alankar.chavan Alankar Chavan (Inactive) made changes -
            Item State Parent values: Stage QA(10202)Level 1 values: On Hold(10215) Parent values: Production QA(10203)Level 1 values: Production Deployed(10221)
            alankar.chavan Alankar Chavan (Inactive) made changes -
            Item State Parent values: Production QA(10203)Level 1 values: Production Deployed(10221) Parent values: Production QA(10203)Level 1 values: In Testing(10218)
            Hide
            alankar.chavan Alankar Chavan (Inactive) added a comment -

            Tested on WT Stage - Stage and Production - 14th Dec 2016
            Working well
            Changes are made as per the suggestion given in attached screen shot

            CC - Deepali Tidke Rakesh Roy Venkatesh Pujari Hrishikesh Deshpande

            Show
            alankar.chavan Alankar Chavan (Inactive) added a comment - Tested on WT Stage - Stage and Production - 14th Dec 2016 Working well Changes are made as per the suggestion given in attached screen shot CC - Deepali Tidke Rakesh Roy Venkatesh Pujari Hrishikesh Deshpande
            alankar.chavan Alankar Chavan (Inactive) made changes -
            Item State Parent values: Production QA(10203)Level 1 values: In Testing(10218) Parent values: Production Complete(10222)Level 1 values: Closed(10223)
            alankar.chavan Alankar Chavan (Inactive) made changes -
            Status Stage Testing [ 10201 ] Pending for Production Approval [ 10301 ]
            alankar.chavan Alankar Chavan (Inactive) made changes -
            Status Pending for Production Approval [ 10301 ] Approved for production [ 10034 ]
            alankar.chavan Alankar Chavan (Inactive) made changes -
            Status Approved for production [ 10034 ] Production Testing [ 10202 ]
            alankar.chavan Alankar Chavan (Inactive) made changes -
            Resolution Fixed [ 1 ]
            Status Production Testing [ 10202 ] Production Complete [ 10028 ]
            alankar.chavan Alankar Chavan (Inactive) made changes -
            Status Production Complete [ 10028 ] Closed [ 6 ]
            alankar.chavan Alankar Chavan (Inactive) logged work - 14/Dec/16 12:41 PM
            • Time Spent:
              0.5h
               

              Prod Testing

            alankar.chavan Alankar Chavan (Inactive) made changes -
            Time Spent 1h [ 3600 ] 1.5h [ 5400 ]
            Worklog Id 13069 [ 13069 ]
            Transition Time In Source Status Execution Times
            shyam sharma (Inactive) made transition -
            New Request Pending for Approval
            8d 23h 35m 1
            shyam sharma (Inactive) made transition -
            Pending for Approval Approved for Development
            4s 1
            shyam sharma (Inactive) made transition -
            Approved for Development In Development
            4s 1
            shyam sharma (Inactive) made transition -
            In Development In LB Testing
            5s 1
            shyam sharma (Inactive) made transition -
            In LB Testing Pending for Stage Approval
            12s 1
            Rakesh Roy (Inactive) made transition -
            Pending for Stage Approval Approved for Stage
            11d 21h 5m 1
            Rakesh Roy (Inactive) made transition -
            Approved for Stage Stage Testing
            2s 1
            Alankar Chavan (Inactive) made transition -
            Stage Testing Pending for Production Approval
            1d 50m 1
            Alankar Chavan (Inactive) made transition -
            Pending for Production Approval Approved for production
            2s 1
            Alankar Chavan (Inactive) made transition -
            Approved for production In Production Testing
            1s 1
            Alankar Chavan (Inactive) made transition -
            In Production Testing Production Complete
            4s 1
            Alankar Chavan (Inactive) made transition -
            Production Complete Closed
            2s 1

              People

              Assignee:
              alankar.chavan Alankar Chavan (Inactive)
              Reporter:
              alankar.chavan Alankar Chavan (Inactive)
              Account Executive:
              Prasanna Karlekar (Inactive)
              Developer:
              surender kumar (Inactive)
              Votes:
              0 Vote for this issue
              Watchers:
              1 Start watching this issue

                Dates

                Created:
                Updated:
                Resolved:
                Dev Due Date:
                Code Review Date:

                  Time Tracking

                  Estimated:
                  Original Estimate - 1h Original Estimate - 1h
                  1h
                  Remaining:
                  Remaining Estimate - 0h
                  0h
                  Logged:
                  Time Spent - 1.5h
                  1.5h