Type:
Change Request
-
Status: Closed
-
Priority:
High
-
Resolution: Unresolved
-
Affects Version/s: None
-
Fix Version/s: None
-
Component/s: None
-
Labels:None
-
Module:ACA - Reports
-
Reported by:Support
-
Company:Prime Healthcare
-
Item State:Development - On Hold
- relates to
-
WT-10032 ACA: Performance Issue-Getting too much time to export the prime files.
-
- Production Complete
-
-
WT-8255 Prime - Full file for Jan 17 and change file Feb 17 onwards
-
- Closed
-
-
WT-9963 Prime Healthcare | Getting error while exporting ACA template.
-
- Closed
-
-
WT-10243 ACA_prime Automation_Cost related fields are rolling out blank on file
-
- Rejected
-
-
WT-12168 ACA : While Exporting ACA files, If the field is Marked as Required and value of that field is blank, not populate complete row
-
- Closed
-
-
WT-12790 ACA Prime - if employee waive his enrollment, and its waive enrollment is terminated then termination date should be blank on file
-
- Closed
-
Field | Original Value | New Value |
---|---|---|
Assignee | Vijay Siddha [ vijays ] | Mahendra Mungase [ mahendra.mungase ] |
Item State | Parent values: Development(10200)Level 1 values: In Analysis(10204) | Parent values: Production QA(10203)Level 1 values: In Testing(10218) |
Status | New Request [ 10029 ] | Pending for Approval [ 10002 ] |
Status | Pending for Approval [ 10002 ] | Approved for Development [ 10003 ] |
Status | Approved for Development [ 10003 ] | In Development [ 10007 ] |
Status | In Development [ 10007 ] | Local Testing [ 10200 ] |
Status | Local Testing [ 10200 ] | Pending for Stage Approval [ 10300 ] |
Status | Pending for Stage Approval [ 10300 ] | Approved for Stage [ 10030 ] |
Status | Approved for Stage [ 10030 ] | Stage Testing [ 10201 ] |
Status | Stage Testing [ 10201 ] | Pending for Production Approval [ 10301 ] |
Status | Pending for Production Approval [ 10301 ] | Approved for production [ 10034 ] |
Status | Approved for production [ 10034 ] | Production Testing [ 10202 ] |
Assignee | Mahendra Mungase [ mahendra.mungase ] | Smita Pawar [ smita.pawar ] |
Production Due Date | 07/Mar/2017 |
Assignee | Smita Pawar [ smita.pawar ] | Revansiddha Gaur [ revansiddha.gaur ] |
-
- Time Spent:
- 0.5h
-
Finding out export field mapping issue
Remaining Estimate | 160h [ 576000 ] | 159.5h [ 574200 ] |
Time Spent | 0.5h [ 1800 ] | |
Worklog Id | 24040 [ 24040 ] |
-
- Time Spent:
- 7h
-
Prime file discussion , template creation and testing
-
- Time Spent:
- 2h
-
Internal discussion, Customization analysis.
Item State | Parent values: Production QA(10203)Level 1 values: In Testing(10218) | Parent values: Development(10200)Level 1 values: In Analysis(10204) |
Remaining Estimate | 159.5h [ 574200 ] | 157.5h [ 567000 ] |
Time Spent | 0.5h [ 1800 ] | 2.5h [ 9000 ] |
Worklog Id | 39756 [ 39756 ] |
-
- Time Spent:
- 2h
- <No comment>
-
- Time Spent:
- 2h
-
Prime file discussion and template updation
-
- Time Spent:
- 2h
- <No comment>
-
- Time Spent:
- 8h
-
Internal discussion for implementation of BenefitsDecisionDate, BenefitsEffectiveDate fields.
Implementation is inprogress..
-
- Time Spent:
- 0.5h
-
Discussion and KT to Smita
-
- Time Spent:
- 2h
- <No comment>
-
- Time Spent:
- 6h
-
Implementation & testing...
Remaining Estimate | 157.5h [ 567000 ] | 149.5h [ 538200 ] |
Time Spent | 2.5h [ 9000 ] | 10.5h [ 37800 ] |
Worklog Id | 41112 [ 41112 ] |
Remaining Estimate | 149.5h [ 538200 ] | 143.5h [ 516600 ] |
Time Spent | 10.5h [ 37800 ] | 16.5h [ 59400 ] |
Worklog Id | 41113 [ 41113 ] |
-
- Time Spent:
- 2h
- <No comment>
Remaining Estimate | 143.5h [ 516600 ] | 136.5h [ 491400 ] |
Time Spent | 16.5h [ 59400 ] | 23.5h [ 84600 ] |
Worklog Id | 41600 [ 41600 ] |
Remaining Estimate | 136.5h [ 491400 ] | 132.5h [ 477000 ] |
Time Spent | 23.5h [ 84600 ] | 27.5h [ 99000 ] |
Worklog Id | 41840 [ 41840 ] |
Remaining Estimate | 132.5h [ 477000 ] | 130.5h [ 469800 ] |
Time Spent | 27.5h [ 99000 ] | 29.5h [ 106200 ] |
Worklog Id | 41877 [ 41877 ] |
Remaining Estimate | 130.5h [ 469800 ] | 128.5h [ 462600 ] |
Time Spent | 29.5h [ 106200 ] | 31.5h [ 113400 ] |
Worklog Id | 41878 [ 41878 ] |
Remaining Estimate | 128.5h [ 462600 ] | 126.5h [ 455400 ] |
Time Spent | 31.5h [ 113400 ] | 33.5h [ 120600 ] |
Worklog Id | 41880 [ 41880 ] |
-
- Time Spent:
- 2h
- <No comment>
Remaining Estimate | 126.5h [ 455400 ] | 124.5h [ 448200 ] |
Time Spent | 33.5h [ 120600 ] | 35.5h [ 127800 ] |
Worklog Id | 41881 [ 41881 ] |
Remaining Estimate | 124.5h [ 448200 ] | 122.5h [ 441000 ] |
Time Spent | 35.5h [ 127800 ] | 37.5h [ 135000 ] |
Worklog Id | 41882 [ 41882 ] |
Remaining Estimate | 122.5h [ 441000 ] | 115.5h [ 415800 ] |
Time Spent | 37.5h [ 135000 ] | 44.5h [ 160200 ] |
Worklog Id | 41907 [ 41907 ] |
Remaining Estimate | 115.5h [ 415800 ] | 113.5h [ 408600 ] |
Time Spent | 44.5h [ 160200 ] | 46.5h [ 167400 ] |
Worklog Id | 41925 [ 41925 ] |
Remaining Estimate | 113.5h [ 408600 ] | 113h [ 406800 ] |
Time Spent | 46.5h [ 167400 ] | 47h [ 169200 ] |
Worklog Id | 41931 [ 41931 ] |
-
- Time Spent:
- 4h
-
Prime file testing & discussion.
-
- Time Spent:
- 4.5h
-
Implementation in progress.
Remaining Estimate | 113h [ 406800 ] | 108.5h [ 390600 ] |
Time Spent | 47h [ 169200 ] | 51.5h [ 185400 ] |
Worklog Id | 42789 [ 42789 ] |
-
- Time Spent:
- 2.5h
-
Automated File unit testing.
Remaining Estimate | 108.5h [ 390600 ] | 106h [ 381600 ] |
Time Spent | 51.5h [ 185400 ] | 54h [ 194400 ] |
Worklog Id | 43047 [ 43047 ] |
-
- Time Spent:
- 5h
-
Discussion with Nandkumar
Analysis of File between Automated & Manual file.
Remaining Estimate | 106h [ 381600 ] | 101h [ 363600 ] |
Time Spent | 54h [ 194400 ] | 59h [ 212400 ] |
Worklog Id | 43278 [ 43278 ] |
-
- Time Spent:
- 4h
- <No comment>
Remaining Estimate | 101h [ 363600 ] | 98.5h [ 354600 ] |
Time Spent | 59h [ 212400 ] | 61.5h [ 221400 ] |
Worklog Id | 43900 [ 43900 ] |
Remaining Estimate | 98.5h [ 354600 ] | 94.5h [ 340200 ] |
Time Spent | 61.5h [ 221400 ] | 65.5h [ 235800 ] |
Worklog Id | 44149 [ 44149 ] |
-
- Time Spent:
- 3h
- <No comment>
-
- Time Spent:
- 4h
-
Coding,Discussion on Review,File verification..
-
- Time Spent:
- 2h
- <No comment>
Remaining Estimate | 94.5h [ 340200 ] | 90.5h [ 325800 ] |
Time Spent | 65.5h [ 235800 ] | 69.5h [ 250200 ] |
Worklog Id | 44903 [ 44903 ] |
-
- Time Spent:
- 6h
-
File testing,coding,discussion.
Remaining Estimate | 90.5h [ 325800 ] | 84.5h [ 304200 ] |
Time Spent | 69.5h [ 250200 ] | 75.5h [ 271800 ] |
Worklog Id | 45545 [ 45545 ] |
-
- Time Spent:
- 8h
-
Code review,coding,unit testing.
-
- Time Spent:
- 2h
- <No comment>
Code Review Date | 16/May/2017 | |
Code Reviewed By | Nandkumar Karlekar [ 11904 ] | |
Item State | Parent values: Development(10200)Level 1 values: In Analysis(10204) | Parent values: Development(10200)Level 1 values: Ready for Review(10208) |
Item State | Parent values: Development(10200)Level 1 values: Ready for Review(10208) | Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) |
Assignee | Revansiddha Gaur [ revansiddha.gaur ] | Smita Pawar [ smita.pawar ] |
Remaining Estimate | 84.5h [ 304200 ] | 82.5h [ 297000 ] |
Time Spent | 75.5h [ 271800 ] | 77.5h [ 279000 ] |
Worklog Id | 46478 [ 46478 ] |
-
- Time Spent:
- 1.5h
-
trunk and lb checkins.
Remaining Estimate | 82.5h [ 297000 ] | 81h [ 291600 ] |
Time Spent | 77.5h [ 279000 ] | 79h [ 284400 ] |
Worklog Id | 46583 [ 46583 ] |
Remaining Estimate | 81h [ 291600 ] | 73h [ 262800 ] |
Time Spent | 79h [ 284400 ] | 87h [ 313200 ] |
Worklog Id | 46588 [ 46588 ] |
Remaining Estimate | 73h [ 262800 ] | 70h [ 252000 ] |
Time Spent | 87h [ 313200 ] | 90h [ 324000 ] |
Worklog Id | 49043 [ 49043 ] |
Remaining Estimate | 70h [ 252000 ] | 68h [ 244800 ] |
Time Spent | 90h [ 324000 ] | 92h [ 331200 ] |
Worklog Id | 49044 [ 49044 ] |
Remaining Estimate | 68h [ 244800 ] | 63h [ 226800 ] |
Time Spent | 92h [ 331200 ] | 97h [ 349200 ] |
Worklog Id | 53096 [ 53096 ] |
Status | Production Testing [ 10202 ] | Reopen in Production [ 10027 ] |
Status | Reopen in Production [ 10027 ] | In Development [ 10007 ] |
Status | In Development [ 10007 ] | Local Testing [ 10200 ] |
Remaining Estimate | 63h [ 226800 ] | 61h [ 219600 ] |
Time Spent | 97h [ 349200 ] | 99h [ 356400 ] |
Worklog Id | 53751 [ 53751 ] |
-
- Time Spent:
- 2h
-
EIN Field code merge & review requested.
-
- Time Spent:
- 1.5h
-
Internal discussion.
Performance optimization of the query
Remaining Estimate | 61h [ 219600 ] | 59.5h [ 214200 ] |
Time Spent | 99h [ 356400 ] | 100.5h [ 361800 ] |
Worklog Id | 54370 [ 54370 ] |
Remaining Estimate | 59.5h [ 214200 ] | 59h [ 212400 ] |
Time Spent | 100.5h [ 361800 ] | 101h [ 363600 ] |
Worklog Id | 54373 [ 54373 ] |
-
- Time Spent:
- 1h
-
File checkins to lb & uirefresh.
Item State | Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) | Parent values: LB QA(10201)Level 1 values: In Testing(10210) |
Remaining Estimate | 59h [ 212400 ] | 58h [ 208800 ] |
Time Spent | 101h [ 363600 ] | 102h [ 367200 ] |
Worklog Id | 55629 [ 55629 ] |
-
- Time Spent:
- 2h
-
Discussion
Template modification
File export
Remaining Estimate | 58h [ 208800 ] | 56h [ 201600 ] |
Time Spent | 102h [ 367200 ] | 104h [ 374400 ] |
Worklog Id | 60002 [ 60002 ] |
Attachment | Prime Checklist QA.xls [ 54161 ] |
Remaining Estimate | 56h [ 201600 ] | 55.5h [ 199800 ] |
Time Spent | 104h [ 374400 ] | 104.5h [ 376200 ] |
Worklog Id | 62110 [ 62110 ] |
-
- Time Spent:
- 1h
-
Internal discussion
Jira Updates
Remaining Estimate | 55.5h [ 199800 ] | 54.5h [ 196200 ] |
Time Spent | 104.5h [ 376200 ] | 105.5h [ 379800 ] |
Worklog Id | 65112 [ 65112 ] |
Assignee | Smita Pawar [ smita.pawar ] | Yogesh Chaudhari [ yogesh.chaudhari ] |
Production Due Date | 07/Mar/2017 | 07/Sep/2017 |
Stage Due Date | 28/Aug/17 [ 2017-08-28 ] |
Remaining Estimate | 54.5h [ 196200 ] | 52.5h [ 189000 ] |
Time Spent | 105.5h [ 379800 ] | 107.5h [ 387000 ] |
Worklog Id | 89928 [ 89928 ] |
Remaining Estimate | 52.5h [ 189000 ] | 46.5h [ 167400 ] |
Time Spent | 107.5h [ 387000 ] | 113.5h [ 408600 ] |
Worklog Id | 89953 [ 89953 ] |
-
- Time Spent:
- 2h
-
Customization setup & discussion for prime file.
-
- Time Spent:
- 6h
-
1. KMC on local for Prime Automation
2. Analysed,discussed and create employee template on local
3. Working to export ACA data for Prime
-
- Time Spent:
- 1.5h
-
Discussion with Yogesh on 1095C manual script execution
Script creation
Testing on Local company
Remaining Estimate | 46.5h [ 167400 ] | 45h [ 162000 ] |
Time Spent | 113.5h [ 408600 ] | 115h [ 414000 ] |
Worklog Id | 90139 [ 90139 ] |
-
- Time Spent:
- 8h
-
Exported Prime file manually and create templates on local and export file .
Analysis of descripencies found in file.
Discussion with the Ramya and Team regarding eligibility processed for Prime.
Remaining Estimate | 45h [ 162000 ] | 37.5h [ 135000 ] |
Time Spent | 115h [ 414000 ] | 122.5h [ 441000 ] |
Worklog Id | 90492 [ 90492 ] |
-
- Time Spent:
- 2.5h
-
Analysis of the employees receiving 1H and 2B in the month they are terminated although they have offer for all month.
Testing
-
- Time Spent:
- 5.5h
-
Discussion & analysis on exported files difference with manual file
-
- Time Spent:
- 7.5h
-
Exported ACA files from manually and automatically and compare both the files.
Analysis of 25 employee difference and worked on same.
Remaining Estimate | 37.5h [ 135000 ] | 35h [ 126000 ] |
Time Spent | 122.5h [ 441000 ] | 125h [ 450000 ] |
Worklog Id | 90577 [ 90577 ] |
Remaining Estimate | 35h [ 126000 ] | 29.5h [ 106200 ] |
Time Spent | 125h [ 450000 ] | 130.5h [ 469800 ] |
Worklog Id | 90599 [ 90599 ] |
-
- Time Spent:
- 1h
-
Issue verification of 1H and 2B
Remaining Estimate | 29.5h [ 106200 ] | 28.5h [ 102600 ] |
Time Spent | 130.5h [ 469800 ] | 131.5h [ 473400 ] |
Worklog Id | 90834 [ 90834 ] |
Remaining Estimate | 28.5h [ 102600 ] | 20.5h [ 73800 ] |
Time Spent | 131.5h [ 473400 ] | 139.5h [ 502200 ] |
Worklog Id | 90953 [ 90953 ] |
Attachment | TechSpec_WT-8296_Prime_Automation_IsRequired_Field_Export.doc [ 70177 ] |
Assignee | Yogesh Chaudhari [ yogesh.chaudhari ] | Revansiddha Gaur [ revansiddha.gaur ] |
Item State | Parent values: LB QA(10201)Level 1 values: In Testing(10210) | Parent values: Development(10200)Level 1 values: On Hold(10207) |
Status | Local Testing [ 10200 ] | Reopen in Local [ 10018 ] |
-
- Time Spent:
- 0.5h
-
Mail about aca file process for 2018
Status | Reopen in Local [ 10018 ] | In Development [ 10007 ] |
Status | In Development [ 10007 ] | Local Testing [ 10200 ] |
Status | Local Testing [ 10200 ] | Pending for Stage Approval [ 10300 ] |
Status | Pending for Stage Approval [ 10300 ] | Approved for Stage [ 10030 ] |
Status | Approved for Stage [ 10030 ] | Stage Testing [ 10201 ] |
Status | Stage Testing [ 10201 ] | Pending for Production Approval [ 10301 ] |
Status | Pending for Production Approval [ 10301 ] | Approved for production [ 10034 ] |
Status | Approved for production [ 10034 ] | Production Testing [ 10202 ] |
Attachment | ACA Prime File Process for year 2018.pdf [ 74044 ] |
Assignee | Revansiddha Gaur [ revansiddha.gaur ] | Amit Thorve [ amitthorve ] |
Resolution | Cancelled [ 10300 ] | |
Status | Production Testing [ 10202 ] | Production Complete [ 10028 ] |
Resolution | Cancelled [ 10300 ] | |
Status | Production Complete [ 10028 ] | Closed [ 6 ] |
-
- Time Spent:
- 0.5h
-
1.Discussion with Prashant for Closing process the tickets
2.Tickets marked as closed by commenting.
Remaining Estimate | 20.5h [ 73800 ] | 20h [ 72000 ] |
Time Spent | 139.5h [ 502200 ] | 140h [ 504000 ] |
Worklog Id | 107135 [ 107135 ] |
Remaining Estimate | 20h [ 72000 ] | 19.5h [ 70200 ] |
Time Spent | 140h [ 504000 ] | 140.5h [ 505800 ] |
Worklog Id | 107139 [ 107139 ] |
Transition | Time In Source Status | Execution Times |
---|
|
3h 48m | 1 |
|
3s | 1 |
|
2s | 1 |
|
123d 1h 32m | 1 |
|
3s | 1 |
|
201d 21h 54m | 1 |
|
66d 19h 57m | 1 |
|
1h 57m | 3 |
|
18s | 2 |
|
6s | 2 |
|
5s | 2 |
|
9s | 2 |
|
6s | 2 |
|
7s | 2 |
|
8m | 1 |
|
7s | 1 |
Please start the template creation