Type:
Bug
-
Status: Closed
-
Priority:
High
-
Resolution: Unresolved
-
Affects Version/s: None
-
Fix Version/s: None
-
Component/s: BenAdmin
-
Labels:
-
Environment:Production
-
Bug Severity:Medium
-
Module:BenAdmin - Report
-
Reported by:Client
-
Company:TIBCO
-
Item State:Production Complete - Closed
-
Sprint:WT Sprint 41
Please see the adjustment issues BCC is having with TIBCO's August bill.
Issue 1: LTD coverage is being unbilled and rebilled at a pro-rated monthly portion. Example: Alec Cross Originally billing for January for Long-Term Disability at $16.25 on the January Invoice. On the August invoice he is being credited for January in the Amount of -$16.25 and being rebilled at $3.67. We did load a new salary effective 1/25/2017, but no billing adjustment should have occurred. The system looks like it is trying to pro-rate for those last 7 days of the month. (16.25/31*7=$3.67)
Other examples: Aaron Shoffa, Adrian Johnson, and many more.
Issue 2: Abay Prajapati terminated 5/31/2017 via a file load that occurred on 6/13/2017. The adjustments on the August invoice look correct with the exception of the COBRA Admin Coverage. COBRA admin did not credit for June or July and COBRA admin is still being billed for August. Even stranger he is being rebilled for January through May which he was previously billed during those billing cycles. Another example of same issue is Shaohua Qu.
Issue 3: Barton Wright his ADD is not age reducing correctly. His age reduction should be the same as life with a volume of $169,000.00. The system for ADD is crediting $110,000 and re-billing at a volume of $260,000 February through current month of August. It looks like the system has not been doing the ADD age reductions correctly from the beginning. The system was reducing the amount to $110,000 versus $169,000
Field | Original Value | New Value |
---|---|---|
Module | Parent values: BenAdmin(10100) | Parent values: BenAdmin(10100)Level 1 values: Report(10109) |
-
- Time Spent:
- 3.5h
-
Issue Analysis
Correction script
Code Fix - In Progress
JIRA status update
Status | Open [ 1 ] | In Development [ 10007 ] |
Assignee | Prasanna Karlekar [ prasanna ] | Debbie Kulling [ dkulling ] |
-
- Time Spent:
- 2.25h
-
Code fix and unit testing for Retro Add appearing with prorated premiums
JIRA Update
Remaining Estimate | 2h [ 7200 ] | |
Original Estimate | 2h [ 7200 ] |
Remaining Estimate | 2h [ 7200 ] | 0.5h [ 1800 ] |
Time Spent | 1.5h [ 5400 ] | |
Worklog Id | 65024 [ 65024 ] |
Attachment | Life Plan.png [ 56201 ] |
Attachment | AD&D Plan.png [ 56202 ] |
Attachment | Payroll Changes.png [ 56203 ] |
-
- Time Spent:
- 2.5h
-
discussion with Prasanna, analysis of age reduction issue and reply to client
-
- Time Spent:
- 5.5h
-
Discussion with Enrollment Team on Age reduction issue
Discussion on returns to be made by Employee-PlanDesign ID or by EnrollmentID
Code fix and Unit testing for retro term scenario
Discussion with QA for TIBCO - Aug 2017 Invoice testing
Audit script modification for Retro Add records verification
Data audit - Issue found in Retro Terms
-
- Time Spent:
- 2h
-
Code changes and unit testing to fix the retro Term adjustment scenario - Need to check different solution as it is failing in some different scenario
JIRA update for TIBCO audit
Remaining Estimate | 0.5h [ 1800 ] | 0h [ 0 ] |
Time Spent | 1.5h [ 5400 ] | 5h [ 18000 ] |
Worklog Id | 65900 [ 65900 ] |
Time Spent | 5h [ 18000 ] | 7.25h [ 26100 ] |
Worklog Id | 65908 [ 65908 ] |
Time Spent | 7.25h [ 26100 ] | 12.75h [ 45900 ] |
Worklog Id | 65911 [ 65911 ] |
Time Spent | 12.75h [ 45900 ] | 14.75h [ 53100 ] |
Worklog Id | 65917 [ 65917 ] |
Time Spent | 14.75h [ 53100 ] | 16.75h [ 60300 ] |
Worklog Id | 66927 [ 66927 ] |
Assignee | Debbie Kulling [ dkulling ] | Prasanna Karlekar [ prasanna ] |
Time Spent | 16.75h [ 60300 ] | 19.25h [ 69300 ] |
Worklog Id | 67861 [ 67861 ] |
Sprint | WT Sprint 34-Bugs [ 79 ] |
Dev Due Date | 04/Aug/2017 |
Code Reviewed By | Prasanna Karlekar [ 11907 ] | |
Dev Estimates | 35 |
-
- Time Spent:
- 1h
-
Generated Invoices with existing procedure and after changing the procedure.
Compared data before and after change
-
- Time Spent:
- 0.5h
-
Issue fix verification
Sprint | WT Sprint 34-Bugs [ 79 ] | WT Sprint 35 - Bugs [ 81 ] |
Company | TIBCO [ 13656 ] |
Time Spent | 19.25h [ 69300 ] | 19.5h [ 70200 ] |
Worklog Id | 72527 [ 72527 ] |
Time Spent | 19.5h [ 70200 ] | 19.75h [ 71100 ] |
Worklog Id | 72536 [ 72536 ] |
Time Spent | 19.75h [ 71100 ] | 20.75h [ 74700 ] |
Worklog Id | 72551 [ 72551 ] |
Time Spent | 20.75h [ 74700 ] | 21.25h [ 76500 ] |
Worklog Id | 72578 [ 72578 ] |
Sprint | WT Sprint 35 - Bugs [ 81 ] |
Time Spent | 21.25h [ 76500 ] | 21.75h [ 78300 ] |
Worklog Id | 75152 [ 75152 ] |
Dev Due Date | 04/Aug/2017 | 04/Aug/2017 |
Item State | Parent values: Development(10200)Level 1 values: On Hold(10207) |
Dev Due Date | 04/Aug/2017 | 04/Oct/2018 |
Dev Due Date | 04/Oct/2018 |
Labels | Invoice_Management |
Root Cause | Bug [ 18430 ] |
Environment_New | Production [ 18442 ] |
Time Spent | 21.75h [ 78300 ] | 22.75h [ 81900 ] |
Worklog Id | 89334 [ 89334 ] |
-
- Time Spent:
- 1h
-
Code check in verification
Query reply
Code Reviewed By | Prasanna Karlekar [ 11907 ] | Jyoti Agarwal [ 16704 ] |
Dev Due Date | 15/Nov/2017 | |
Developer | Prasanna Karlekar [ prasanna ] |
Item State | Parent values: Development(10200)Level 1 values: On Hold(10207) | Parent values: Development(10200)Level 1 values: In Progress(10206) |
Item State | Parent values: Development(10200)Level 1 values: In Progress(10206) | Parent values: Development(10200)Level 1 values: On Hold(10207) |
Item State | Parent values: Development(10200)Level 1 values: On Hold(10207) | Parent values: Development(10200)Level 1 values: In Progress(10206) |
Assignee | Prasanna Karlekar [ prasanna ] | Parmeshwar Jumbad [ parmeshwar.jumbade ] |
Approval status | Approved for development [ 18453 ] | |
Attachment | FW Development approval for 9-Nov-2017.msg [ 68120 ] | |
Attachment | FW Development approval for 9-Nov-2017.msg [ 68121 ] |
Dev Due Date | 15/Nov/2017 | 05/Dec/2017 |
-
- Time Spent:
- 0.75h
-
Verified output after applying condition - Scenarios getting failed
Sprint | WT Sprint 41 - Bugs [ 95 ] |
-
- Time Spent:
- 0.5h
-
Discussion
JIRA update
Dev Due Date | 05/Dec/2017 | 12/Dec/2017 |
Dev Estimates | 35 | 40 |
QA | Venkatesh Pujari [ venkatesh.pujari ] | |
QA Estimates | 8 |
Development Approval | Yes [ 18474 ] |
Stage Due Date | 22/Dec/17 [ 2017-12-22 ] |
Assignee | Parmeshwar Jumbad [ parmeshwar.jumbade ] | Prasanna Karlekar [ prasanna ] |
Attachment | FW 1211 Sprint - Development Approval.msg [ 69872 ] |
Item State | Parent values: Development(10200)Level 1 values: In Progress(10206) | Parent values: Development(10200)Level 1 values: Ready for Local Testing(10209) |
Code Reviewed By | Jyoti Agarwal [ 16704 ] | Prasanna Karlekar [ 11907 ] |
Item State | Parent values: Development(10200)Level 1 values: Ready for Local Testing(10209) | Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) |
Assignee | Prasanna Karlekar [ prasanna ] | Venkatesh Pujari [ venkatesh.pujari ] |
Item State | Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) | Parent values: LB QA(10201)Level 1 values: In Testing(10210) |
Status | In Development [ 10007 ] | Local Testing [ 10200 ] |
Status | Local Testing [ 10200 ] | Reopen in Local [ 10018 ] |
Item State | Parent values: LB QA(10201)Level 1 values: In Testing(10210) | Parent values: LB QA(10201)Level 1 values: Re-open(10212) |
Time Spent | 22.75h [ 81900 ] | 26.75h [ 96300 ] |
Worklog Id | 96293 [ 96293 ] |
Assignee | Venkatesh Pujari [ venkatesh.pujari ] | Prasanna Karlekar [ prasanna ] |
Status | Reopen in Local [ 10018 ] | In Development [ 10007 ] |
Item State | Parent values: LB QA(10201)Level 1 values: Re-open(10212) | Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) |
-
- Time Spent:
- 2.5h
-
Scenario testing - First Invoice 9 scenarios with different Add/Term Policies combinations completed
Code check in
Scenario analysis and fix when cost is changed as per ageband
Email communication
Time Spent | 26.75h [ 96300 ] | 29.25h [ 105300 ] |
Worklog Id | 96752 [ 96752 ] |
Assignee | Prasanna Karlekar [ prasanna ] | Sachin Hingole [ sachin.hingole ] |
Item State | Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) | Parent values: LB QA(10201)Level 1 values: In Testing(10210) |
Assignee | Sachin Hingole [ sachin.hingole ] | Venkatesh Pujari [ venkatesh.pujari ] |
Status | In Development [ 10007 ] | Local Testing [ 10200 ] |
Time Spent | 29.25h [ 105300 ] | 32.25h [ 116100 ] |
Worklog Id | 96816 [ 96816 ] |
-
- Time Spent:
- 2.5h
-
3C updates
Scenario Testing - Tier changes (In Progress)
Status | Local Testing [ 10200 ] | Reopen in Local [ 10018 ] |
Item State | Parent values: LB QA(10201)Level 1 values: In Testing(10210) | Parent values: LB QA(10201)Level 1 values: Re-open(10212) |
Time Spent | 32.25h [ 116100 ] | 36.25h [ 130500 ] |
Worklog Id | 97058 [ 97058 ] |
Assignee | Venkatesh Pujari [ venkatesh.pujari ] | Jyoti Agrawal [ jyoti.agrawal ] |
Time Spent | 36.25h [ 130500 ] | 38.75h [ 139500 ] |
Worklog Id | 97084 [ 97084 ] |
Status | Reopen in Local [ 10018 ] | In Development [ 10007 ] |
Attachment | Invoice_Scenarios_TestData.xlsx [ 70479 ] |
Assignee | Jyoti Agrawal [ jyoti.agrawal ] | Venkatesh Pujari [ venkatesh.pujari ] |
Status | In Development [ 10007 ] | Local Testing [ 10200 ] |
Item State | Parent values: LB QA(10201)Level 1 values: Re-open(10212) | Parent values: LB QA(10201)Level 1 values: In Testing(10210) |
Attachment | Invoice_Scenarios_TestData.xlsx [ 70479 ] |
Attachment | Scenarios.xls [ 70494 ] |
Time Spent | 38.75h [ 139500 ] | 41.75h [ 150300 ] |
Worklog Id | 97184 [ 97184 ] |
-
- Time Spent:
- 2.5h
-
Scenario discussion and verification for Self Insured Component issue when made non billable
Tier changes verification and Age band change scenario verification
Item State | Parent values: LB QA(10201)Level 1 values: In Testing(10210) | Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) |
Comment |
[ Hi [~jyoti.agrawal], Please find the scenario for which the system is not working as per expectation:- Self Insured components for E+SP tier are 60$ and 80$ both billable. Now I enroll the EE + SP in the Venky SI plan effective from 08/01/2017. Now generated the Invoice for Dec 2017 month. Proper billing and adjustment records were displayed on the invoice. Now change one Self Insured component to Non- Billable and generate the Invoice for jan 2018 month. We can see proper billing for Jan 2018 month and also we can see that credits have been given to the EE, but billable components cost is not charged for this EE. *REOPEN* [~prasanna],[~sachin.hingole] Thanks, Venkatesh ] |
-
- Time Spent:
- 7.5h
-
Testing of Retro Add and Retro Term scenarios.
Item State | Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) | Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213) |
Time Spent | 41.75h [ 150300 ] | 49.25h [ 177300 ] |
Worklog Id | 97366 [ 97366 ] |
-
- Time Spent:
- 2.5h
-
Age band scenario repro on LB
Could not repro the scenario on LB
Changes verified on existing data
Item State | Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213) | Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602) |
Deployment Approval | Approved for stage deployment [ 18455 ] | |
Production Due Date | 29/Dec/2017 |
Time Spent | 49.25h [ 177300 ] | 50h [ 180000 ] |
Worklog Id | 97901 [ 97901 ] |
Status | Local Testing [ 10200 ] | Stage Testing [ 10201 ] |
Item State | Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602) | Parent values: Stage QA(10202)Level 1 values: In Testing(10214) |
Time Spent | 50h [ 180000 ] | 52.5h [ 189000 ] |
Worklog Id | 98010 [ 98010 ] |
Time Spent | 52.5h [ 189000 ] | 55h [ 198000 ] |
Worklog Id | 98020 [ 98020 ] |
Item State | Parent values: Stage QA(10202)Level 1 values: In Testing(10214) | Parent values: Stage QA(10202)Level 1 values: Ready for Production(10217) |
Time Spent | 55h [ 198000 ] | 61h [ 219600 ] |
Worklog Id | 98076 [ 98076 ] |
Item State | Parent values: Stage QA(10202)Level 1 values: Ready for Production(10217) | Parent values: Production QA(10203)Level 1 values: Production Deployed(10221) |
Comments |
Hi All, Following point has been approved for production deployment on 12/29 Regards Gaurav |
|
Deployment Approval | Approved for stage deployment [ 18455 ] | Approved for production deployment [ 18457 ] |
Status | Stage Testing [ 10201 ] | Production Testing [ 10202 ] |
Item State | Parent values: Production QA(10203)Level 1 values: Production Deployed(10221) | Parent values: Production QA(10203)Level 1 values: In Testing(10218) |
Item State | Parent values: Production QA(10203)Level 1 values: In Testing(10218) | Parent values: Production Complete(10222)Level 1 values: Closed(10223) |
Assignee | Venkatesh Pujari [ venkatesh.pujari ] | Debbie Kulling [ dkulling ] |
Resolution | Fixed [ 1 ] | |
Status | Production Testing [ 10202 ] | Production Complete [ 10028 ] |
Time Spent | 61h [ 219600 ] | 68.5h [ 246600 ] |
Worklog Id | 99049 [ 99049 ] |
Time Spent | 68.5h [ 246600 ] | 69h [ 248400 ] |
Worklog Id | 99086 [ 99086 ] |
Time Spent | 69h [ 248400 ] | 69.5h [ 250200 ] |
Worklog Id | 99097 [ 99097 ] |
Time Spent | 69.5h [ 250200 ] | 70.25h [ 252900 ] |
Worklog Id | 99106 [ 99106 ] |
Remaining Estimate | 0h [ 0 ] | 0.75h [ 2700 ] |
Time Spent | 70.25h [ 252900 ] | 69.5h [ 250200 ] |
Worklog Id | 99106 [ 99106 ] | |
Worklog Time Spent | 0.75h [ 2700 ] |
Resolution | Done [ 10000 ] | |
Status | Production Complete [ 10028 ] | Closed [ 6 ] |
Transition | Time In Source Status | Execution Times |
---|
|
1d 16h 56m | 1 |
|
1d 22h 47m | 2 |
|
7h 45m | 2 |
|
151d 15h 10m | 3 |
|
6d 18h 9m | 1 |
|
2d 51m | 1 |
|
4d 6h 9m | 1 |
|
55d 9h 59m | 1 |
Do you think this issue will be resolved today? BCC needs to send the August invoice out.