Uploaded image for project: 'WORKTERRA'
  1. WORKTERRA
  2. WT-11437

Town of Cary- Rate issue (PROD)

    Details

    • Type: Bug
    • Status: Production Complete
    • Priority: High
    • Resolution: Done
    • Affects Version/s: None
    • Fix Version/s: None
    • Component/s: None
    • Environment:
      Production
    • Bug Severity:
      Medium
    • Module:
      BenAdmin - EDS
    • Reported by:
      Support
    • Company:
      Town of Cary
    • Item State:
      Production Complete - Closed
    • Sprint:
      WT Sprint 38 - Bugs, WT Sprint 40 - Bugs

      Description

      Per the CS :
      Hello,
      The EE cost isn't showing up on the Confirmation Statement for the "Retiree Health Plan." There should be a premium cost of $718.14. I checked the rates on the Y drive and it reflects the same EE cost. The cost is showing in WT in the "2017 Retiree Health 0" rate. I waived and saved the plan and it didn't update. Please advise...
      Thanks!
      CT:
      We have pulled a report to show an example. See below.

      For Bobby Hunter, His rates are not coming down on the conformation statement.

      The pull down on the Demographic page does not have a (select button)

      For Dawn Cronin, She also has the zero selected but her conformation shows an amount.

      Can you please let us know what is going on were some of the EE's are getting rates and some are not?

      Thank you,
      Yashau
      Please ref: CT-2699

        Attachments

          Issue Links

            Activity

            Transition Time In Source Status Execution Times
            Vinanti Yadav (Inactive) made transition -
            Open In Development
            56m 24s 1
            Priya Dhamande (Inactive) made transition -
            Stage Testing Reopened in Stage
            1d 4h 15m 1
            Jyotibala Pardeshi (Inactive) made transition -
            Reopened in Stage In Development
            9d 20h 19m 1
            Jyotibala Pardeshi (Inactive) made transition -
            In Development Rejected
            2d 23h 29m 1
            Jyotibala Pardeshi (Inactive) made transition -
            Rejected Reopen
            4m 45s 1
            Jyotibala Pardeshi (Inactive) made transition -
            Reopen In Development
            6s 1
            Rakesh Roy (Inactive) made transition -
            In Development In LB Testing
            12d 21h 28m 2
            Rakesh Roy (Inactive) made transition -
            In LB Testing Stage Testing
            2d 19h 19m 2
            Rakesh Roy (Inactive) made transition -
            Stage Testing In Production Testing
            1d 2h 15m 1
            Rakesh Roy (Inactive) made transition -
            In Production Testing Production Complete
            55s 1

              People

              Assignee:
              Yashau.Macshate Yashau MacShate (Inactive)
              Reporter:
              Yashau.Macshate Yashau MacShate (Inactive)
              Developer:
              Jyotibala Pardeshi (Inactive)
              QA:
              Priya Dhamande (Inactive)
              Votes:
              0 Vote for this issue
              Watchers:
              7 Start watching this issue

                Dates

                Created:
                Updated:
                Resolved:
                Dev Due Date:
                Pre-Prod Due Date:
                Code Review Date:

                  Time Tracking

                  Estimated:
                  Original Estimate - 8h Original Estimate - 8h
                  8h
                  Remaining:
                  Remaining Estimate - 0h
                  0h
                  Logged:
                  Time Spent - 33h 16m
                  33h 16m