Uploaded image for project: 'WORKTERRA'
  1. WORKTERRA
  2. WT-7380

WT -> BCC Invoice Enhancement -> Duplicate Adjustment Entries in case of few scenarios

    Details

    • Type: Bug
    • Status: Closed
    • Priority: High
    • Resolution: Done
    • Affects Version/s: None
    • Fix Version/s: None
    • Component/s: None
    • Labels:
      None
    • Environment:
      Stage
    • Module:
      BenAdmin - Report
    • Reported by:
      Harbinger
    • Item State:
      Production Complete - Closed

      Description

      TIBCO
      Plan - Say Voluntary Employee Life
      Employee Say - SUBRAMANIAM SWAMINATHAN

      • employee is enrolled in above plan with say $30000 coverage amount and $20 cost
      • fetched invoice for Nov 2016 : shown the above entry in billing details [Nov 2016] and billing adjustment details [Jan to Oct 2016]
      • I enrddolled that employee from 01/01/2016 with say $40000 coverage amount and $30 cost
      • with this the enrollment from 09/01/2016 gets deleted- employee just have a single enrollment from 01/01/2016 to 12/31/2016 with $40000 coverage amount and $30 cost
      • fetched invoice for Dec 2016

      Expected & Actual Result :

      Billing for Dec 2016 : $40000 coverage and $30 cost
      Billing Adjustment from Jan to Nov 2016 : $30000 coverage and - $20 cost

      On extra entry is shown Billing Adjustment from Jan to Nov 2016 : $30000 coverage and $20 cost which is wrong

      CC - Jyoti Agrawal Deepali Tidke Rakesh Roy Venkatesh Pujari Hrishikesh Deshpande

        Attachments

          Issue Links

            Activity

            alankar.chavan Alankar Chavan (Inactive) created issue -
            alankar.chavan Alankar Chavan (Inactive) made changes -
            Field Original Value New Value
            Link This issue relates to WT-6331 [ WT-6331 ]
            khandu.kshirsagar Khandu Kshirsagar (Inactive) made changes -
            Item State Parent values: LB QA(10201)Level 1 values: LB Deployed(11600)
            prasanna Prasanna Karlekar (Inactive) made changes -
            Assignee Prasanna Karlekar [ prasanna ] Jyoti Agrawal [ jyoti.agrawal ]
            prasanna Prasanna Karlekar (Inactive) made changes -
            Dev Due Date 24/Feb/2017
            prasanna Prasanna Karlekar (Inactive) made changes -
            Dev Due Date 24/Feb/2017 15/Feb/2017
            jyoti.agrawal Jyoti Agrawal (Inactive) logged work - 14/Feb/17 11:17 AM
            • Time Spent:
              3h
               

              Analysis, coding, unit testing

            jyoti.agrawal Jyoti Agrawal (Inactive) made changes -
            Assignee Jyoti Agrawal [ jyoti.agrawal ] Venkatesh Pujari [ venkatesh.pujari ]
            jyoti.agrawal Jyoti Agrawal (Inactive) made changes -
            Remaining Estimate 5h [ 18000 ] 2h [ 7200 ]
            Time Spent 3h [ 10800 ]
            Worklog Id 25149 [ 25149 ]
            Hide
            venkatesh.pujari Venkatesh Pujari (Inactive) added a comment -

            Tested this on LB on CAISO company. System is displaying proper adjustment as per expectation.

            This is ready for Stage.

            Prasanna Karlekar,Jyoti Agrawal

            Thanks,
            Venkatesh

            Show
            venkatesh.pujari Venkatesh Pujari (Inactive) added a comment - Tested this on LB on CAISO company. System is displaying proper adjustment as per expectation. This is ready for Stage. Prasanna Karlekar , Jyoti Agrawal Thanks, Venkatesh
            venkatesh.pujari Venkatesh Pujari (Inactive) made changes -
            Status Open [ 1 ] In Development [ 10007 ]
            venkatesh.pujari Venkatesh Pujari (Inactive) made changes -
            Status In Development [ 10007 ] Local Testing [ 10200 ]
            venkatesh.pujari Venkatesh Pujari (Inactive) made changes -
            Item State Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213)
            venkatesh.pujari Venkatesh Pujari (Inactive) made changes -
            Remaining Estimate 2h [ 7200 ] 0.5h [ 1800 ]
            Time Spent 3h [ 10800 ] 4.5h [ 16200 ]
            Worklog Id 25376 [ 25376 ]
            venkatesh.pujari Venkatesh Pujari (Inactive) logged work - 16/Feb/17 06:15 PM
            • Time Spent:
              1.5h
               

              LB Testing

            jyoti.agrawal Jyoti Agrawal (Inactive) made changes -
            Developer Jyoti Agrawal [ jyoti.agrawal ]
            jyoti.agrawal Jyoti Agrawal (Inactive) made changes -
            Code Reviewed By Prasanna Karlekar [ 11907 ]
            khandu.kshirsagar Khandu Kshirsagar (Inactive) made changes -
            Item State Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213) Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602)
            venkatesh.pujari Venkatesh Pujari (Inactive) made changes -
            Status Local Testing [ 10200 ] Stage Testing [ 10201 ]
            venkatesh.pujari Venkatesh Pujari (Inactive) made changes -
            Item State Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602) Parent values: Stage QA(10202)Level 1 values: In Testing(10214)
            venkatesh.pujari Venkatesh Pujari (Inactive) logged work - 22/Feb/17 09:18 AM
            • Time Spent:
              1h
               
              <No comment>
            Hide
            venkatesh.pujari Venkatesh Pujari (Inactive) added a comment -

            Tested this on Stage on AFI For Hspl company. System is displaying proper adjustment as per expectation.

            This is ready for Production.

            Prasanna Karlekar,Jyoti Agrawal

            Thanks,
            Venkatesh

            Show
            venkatesh.pujari Venkatesh Pujari (Inactive) added a comment - Tested this on Stage on AFI For Hspl company. System is displaying proper adjustment as per expectation. This is ready for Production. Prasanna Karlekar , Jyoti Agrawal Thanks, Venkatesh
            venkatesh.pujari Venkatesh Pujari (Inactive) made changes -
            Remaining Estimate 0.5h [ 1800 ] 0h [ 0 ]
            Time Spent 4.5h [ 16200 ] 5.5h [ 19800 ]
            Worklog Id 26562 [ 26562 ]
            venkatesh.pujari Venkatesh Pujari (Inactive) made changes -
            Item State Parent values: Stage QA(10202)Level 1 values: In Testing(10214) Parent values: Stage QA(10202)Level 1 values: Ready for Production(10217)
            ashwin.wankhede Ashwin Wankhede (Inactive) made changes -
            Item State Parent values: Stage QA(10202)Level 1 values: Ready for Production(10217) Parent values: Production QA(10203)Level 1 values: Production Deployed(10221)
            venkatesh.pujari Venkatesh Pujari (Inactive) made changes -
            Status Stage Testing [ 10201 ] Production Testing [ 10202 ]
            Hide
            venkatesh.pujari Venkatesh Pujari (Inactive) added a comment -

            Tested this on Production on AFI For Hspl company. System is displaying proper adjustment as per expectation.

            Prasanna Karlekar,Jyoti Agrawal

            Thanks,
            Venkatesh

            Show
            venkatesh.pujari Venkatesh Pujari (Inactive) added a comment - Tested this on Production on AFI For Hspl company. System is displaying proper adjustment as per expectation. Prasanna Karlekar , Jyoti Agrawal Thanks, Venkatesh
            venkatesh.pujari Venkatesh Pujari (Inactive) logged work - 24/Feb/17 10:12 AM
            • Time Spent:
              1h
               

              Prod Testing

            venkatesh.pujari Venkatesh Pujari (Inactive) made changes -
            Resolution Fixed [ 1 ]
            Status Production Testing [ 10202 ] Production Complete [ 10028 ]
            venkatesh.pujari Venkatesh Pujari (Inactive) made changes -
            Item State Parent values: Production QA(10203)Level 1 values: Production Deployed(10221) Parent values: Production Complete(10222)Level 1 values: Closed(10223)
            venkatesh.pujari Venkatesh Pujari (Inactive) made changes -
            Time Spent 5.5h [ 19800 ] 6.5h [ 23400 ]
            Worklog Id 27104 [ 27104 ]
            venkatesh.pujari Venkatesh Pujari (Inactive) made changes -
            Status Production Complete [ 10028 ] Closed [ 6 ]
            satyap Satya made changes -
            Environment_New Stage [ 18443 ]
            Transition Time In Source Status Execution Times
            Venkatesh Pujari (Inactive) made transition -
            Open In Development
            50d 23h 23m 1
            Venkatesh Pujari (Inactive) made transition -
            In Development In LB Testing
            2s 1
            Venkatesh Pujari (Inactive) made transition -
            In LB Testing Stage Testing
            6d 1h 38m 1
            Venkatesh Pujari (Inactive) made transition -
            Stage Testing In Production Testing
            1d 20h 17m 1
            Venkatesh Pujari (Inactive) made transition -
            In Production Testing Production Complete
            6h 1
            Venkatesh Pujari (Inactive) made transition -
            Production Complete Closed
            22s 1

              People

              Assignee:
              venkatesh.pujari Venkatesh Pujari (Inactive)
              Reporter:
              alankar.chavan Alankar Chavan (Inactive)
              Developer:
              Jyoti Agrawal (Inactive)
              Votes:
              0 Vote for this issue
              Watchers:
              2 Start watching this issue

                Dates

                Created:
                Updated:
                Resolved:
                Dev Due Date:

                  Time Tracking

                  Estimated:
                  Original Estimate - 5h Original Estimate - 5h
                  5h
                  Remaining:
                  Remaining Estimate - 0h
                  0h
                  Logged:
                  Time Spent - 6.5h
                  6.5h