Uploaded image for project: 'WORKTERRA'
  1. WORKTERRA
  2. WT-8451

Qualifying Events - Error with Tunnel

    Details

    • Type: Bug
    • Status: Closed
    • Priority: Critical
    • Resolution: Done
    • Affects Version/s: None
    • Fix Version/s: None
    • Component/s: ACA
    • Labels:
      None
    • Environment:
      Production
    • Bug Severity:
      Medium
    • Module:
      Exchange
    • Reported by:
      Support
    • Item State:
      Production Complete - Closed
    • Issue Importance:
      Must Have

      Description

      Hi Dev -

      I have had 2 clients that are having issues with Qualifying Events -

      Example 1 - Five Guys (Exchange) - Employee Ryan Boles - This employee should be able to update benefits through the tunnel - they are not getting the needed pages - After the tunnel the employee is able to use the umbrella to enroll but they should be getting the tunnel pages.

      Example 2 - SBM - The employee is Tuan Bui - The spouse page is not showing through the tunnel and we are not able to get this to show -

      All of these we are from the employee view not the admin -

      Please review - Five Guys is higher priority if you can review.

      Thanks!

      Jenni

        Attachments

        1. LB-1.png
          LB-1.png
          288 kB
        2. LB-2.png
          LB-2.png
          182 kB
        3. LB-3.png
          LB-3.png
          222 kB
        4. LB-4.png
          LB-4.png
          183 kB

          Issue Links

            Activity

            jjsassy99 Jennifer Johnson (Inactive) created issue -
            Show
            Traci.Simpson@ebsbenefits.com Traci Simpson (Inactive) added a comment - Lorena.Nava@ebsbenefits.com Traci Simpson
            Show
            vijays Vijay Siddha (Inactive) added a comment - CC: Jyoti Mayne , Satya , Hrishikesh Deshpande , Mandar Kulkarni
            vijays Vijay Siddha (Inactive) made changes -
            Field Original Value New Value
            Assignee Vijay Siddha [ vijays ] Avnish Yadav [ avnish.yadav ]
            avnish.yadav Avnish Yadav (Inactive) made changes -
            Status Open [ 1 ] In Development [ 10007 ]
            avnish.yadav Avnish Yadav (Inactive) made changes -
            Link This issue relates to WT-8472 [ WT-8472 ]
            Hide
            avnish.yadav Avnish Yadav (Inactive) added a comment -

            Hi Jennifer Johnson,

            Regarding SBM QE Issue:- We have created another WT-8472 jira for this issue.

            Regarding Five Guys QE Issue:- We have fixed this issue in our local environment and our unit testing is in-progress.Tomorrow (02/16/2017 IST), we will update you on same.

            Thanks,
            Avnish Y

            CC-- Jyoti Mayne

            Show
            avnish.yadav Avnish Yadav (Inactive) added a comment - Hi Jennifer Johnson , Regarding SBM QE Issue:- We have created another WT-8472 jira for this issue. Regarding Five Guys QE Issue:- We have fixed this issue in our local environment and our unit testing is in-progress.Tomorrow (02/16/2017 IST), we will update you on same. Thanks, Avnish Y CC-- Jyoti Mayne
            avnish.yadav Avnish Yadav (Inactive) logged work - 15/Feb/17 06:25 PM
            • Time Spent:
              8h
               
              <No comment>
            avnish.yadav Avnish Yadav (Inactive) made changes -
            Code Reviewed By Swapnil Pandhare [ 11900 ]
            Item State Parent values: Development(10200)Level 1 values: Ready for Local Testing(10209)
            avnish.yadav Avnish Yadav (Inactive) made changes -
            Status In Development [ 10007 ] Local Testing [ 10200 ]
            swapnil.pandhare Swapnil Pandhare (Inactive) logged work - 16/Feb/17 09:52 AM
            • Time Spent:
              1.5h
               

              Discussion with Avnish for exchange code fix and Code review

            Hide
            avnish.yadav Avnish Yadav (Inactive) added a comment -

            Hi Hrishikesh Deshpande,

            Please refer following 3'C for this Five Guys QE Issue:-

            Concern:- In case of QE employee not getting Exchange related pages in Workflow.
            Cause :- For QE, following exchange related page was not implemented.
            1. Health Profile
            2. Questionnaire
            3. Recommend Plans
            4. Select Your Plans

            Correction:- We have fixed this issue by implemented exchange related page in code.

            Please verify the same at your end and let us know in case of any issue/concern.

            Thanks,
            Avnish Y

            CC-- Jyoti Mayne,Satya

            Show
            avnish.yadav Avnish Yadav (Inactive) added a comment - Hi Hrishikesh Deshpande , Please refer following 3'C for this Five Guys QE Issue:- Concern:- In case of QE employee not getting Exchange related pages in Workflow. Cause :- For QE, following exchange related page was not implemented. 1. Health Profile 2. Questionnaire 3. Recommend Plans 4. Select Your Plans Correction:- We have fixed this issue by implemented exchange related page in code. Please verify the same at your end and let us know in case of any issue/concern. Thanks, Avnish Y CC-- Jyoti Mayne , Satya
            khandu.kshirsagar Khandu Kshirsagar (Inactive) made changes -
            Item State Parent values: Development(10200)Level 1 values: Ready for Local Testing(10209) Parent values: LB QA(10201)Level 1 values: LB Deployed(11600)
            hrishikesh.deshpande Hrishikesh Deshpande (Inactive) made changes -
            Assignee Avnish Yadav [ avnish.yadav ] Hrishikesh Deshpande [ hrishikesh.deshpande ]
            Hide
            hrishikesh.deshpande Hrishikesh Deshpande (Inactive) added a comment -

            Hi Jennifer Johnson,

            We have deploy this fix on our Local. We will move it on Stage and on Production as per regular patch process.

            Stage deployment date- 02/20
            Production deployment date- 02/21

            Thanks,
            Hrishikesh.

            Show
            hrishikesh.deshpande Hrishikesh Deshpande (Inactive) added a comment - Hi Jennifer Johnson , We have deploy this fix on our Local. We will move it on Stage and on Production as per regular patch process. Stage deployment date- 02/20 Production deployment date- 02/21 Thanks, Hrishikesh.
            hrishikesh.deshpande Hrishikesh Deshpande (Inactive) made changes -
            Account Executive Jennifer Fernandes [ jjsassy99 ]
            Component/s Exchange [ 10003 ]
            Developer Avnish Yadav [ avnish.yadav ]
            Issue Importance Must Have [ 11800 ]
            Production Due Date 21/Feb/2017
            QA Rajendra Joshi [ rajendraj ]
            Severity Simple [ 13101 ] Medium [ 13102 ]
            Stage Due Date 20/Feb/17 [ 2017-02-20 ]
            Remaining Estimate 3h [ 10800 ]
            Original Estimate 3h [ 10800 ]
            hrishikesh.deshpande Hrishikesh Deshpande (Inactive) made changes -
            Assignee Hrishikesh Deshpande [ hrishikesh.deshpande ] Rajendra Joshi [ rajendraj ]
            rajendraj Rajendra Joshi (Inactive) made changes -
            Assignee Rajendra Joshi [ rajendraj ] Hrishikesh Deshpande [ hrishikesh.deshpande ]
            hrishikesh.deshpande Hrishikesh Deshpande (Inactive) made changes -
            Item State Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213)
            hrishikesh.deshpande Hrishikesh Deshpande (Inactive) made changes -
            Assignee Hrishikesh Deshpande [ hrishikesh.deshpande ] Rajendra Joshi [ rajendraj ]
            Hide
            rajendraj Rajendra Joshi (Inactive) added a comment -

            Verified on LB using company Five Guys. Above issue is fixed now.

            Show
            rajendraj Rajendra Joshi (Inactive) added a comment - Verified on LB using company Five Guys. Above issue is fixed now.
            rajendraj Rajendra Joshi (Inactive) made changes -
            Remaining Estimate 3h [ 10800 ] 2h [ 7200 ]
            Time Spent 1h [ 3600 ]
            Worklog Id 26023 [ 26023 ]
            avnish.yadav Avnish Yadav (Inactive) made changes -
            Remaining Estimate 2h [ 7200 ] 0h [ 0 ]
            Time Spent 1h [ 3600 ] 9h [ 32400 ]
            Worklog Id 26027 [ 26027 ]
            khandu.kshirsagar Khandu Kshirsagar (Inactive) made changes -
            Item State Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213) Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602)
            swapnil.pandhare Swapnil Pandhare (Inactive) made changes -
            Time Spent 9h [ 32400 ] 10.5h [ 37800 ]
            Worklog Id 26052 [ 26052 ]
            Hide
            rajendraj Rajendra Joshi (Inactive) added a comment -

            Verified on Stage using company five guys for hspl. In employee flow, number of screens are changing on save and continue button.

            Show
            rajendraj Rajendra Joshi (Inactive) added a comment - Verified on Stage using company five guys for hspl. In employee flow, number of screens are changing on save and continue button.
            rajendraj Rajendra Joshi (Inactive) made changes -
            Assignee Rajendra Joshi [ rajendraj ] Avnish Yadav [ avnish.yadav ]
            rajendraj Rajendra Joshi (Inactive) made changes -
            Item State Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602) Parent values: Stage QA(10202)Level 1 values: Re-open(10216)
            rajendraj Rajendra Joshi (Inactive) made changes -
            Status Local Testing [ 10200 ] Stage Testing [ 10201 ]
            rajendraj Rajendra Joshi (Inactive) made changes -
            Resolution Unresolved [ 10200 ]
            Status Stage Testing [ 10201 ] Reopen in Stage [ 10023 ]
            avnish.yadav Avnish Yadav (Inactive) made changes -
            Status Reopen in Stage [ 10023 ] In Development [ 10007 ]
            avnish.yadav Avnish Yadav (Inactive) made changes -
            Item State Parent values: Stage QA(10202)Level 1 values: Re-open(10216) Parent values: Development(10200)Level 1 values: Ready for Local Testing(10209)
            avnish.yadav Avnish Yadav (Inactive) logged work - 20/Feb/17 05:15 PM
            • Time Spent:
              2h
               
              <No comment>
            rajendraj Rajendra Joshi (Inactive) logged work - 21/Feb/17 04:41 AM
            • Time Spent:
              1h
               

              stage testing

            rajendraj Rajendra Joshi (Inactive) made changes -
            Time Spent 10.5h [ 37800 ] 11.5h [ 41400 ]
            Worklog Id 26234 [ 26234 ]
            rajendraj Rajendra Joshi (Inactive) logged work - 21/Feb/17 05:41 AM
            • Time Spent:
              1h
               
              <No comment>
            khandu.kshirsagar Khandu Kshirsagar (Inactive) made changes -
            Item State Parent values: Development(10200)Level 1 values: Ready for Local Testing(10209) Parent values: LB QA(10201)Level 1 values: LB Deployed(11600)
            avnish.yadav Avnish Yadav (Inactive) made changes -
            Status In Development [ 10007 ] Local Testing [ 10200 ]
            avnish.yadav Avnish Yadav (Inactive) made changes -
            Assignee Avnish Yadav [ avnish.yadav ] Rajendra Joshi [ rajendraj ]
            avnish.yadav Avnish Yadav (Inactive) logged work - 21/Feb/17 05:18 PM
            • Time Spent:
              2h
               
              <No comment>
            Hide
            rajendraj Rajendra Joshi (Inactive) added a comment -

            Verified on LB using company five guys. Number of pages are displayed 14 onload. but as user continues, they becomes 13. PFA screen shot.

            Show
            rajendraj Rajendra Joshi (Inactive) added a comment - Verified on LB using company five guys. Number of pages are displayed 14 onload. but as user continues, they becomes 13. PFA screen shot.
            rajendraj Rajendra Joshi (Inactive) made changes -
            Attachment LB-1.png [ 40366 ]
            Attachment LB-2.png [ 40367 ]
            rajendraj Rajendra Joshi (Inactive) made changes -
            Item State Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) Parent values: LB QA(10201)Level 1 values: Re-open(10212)
            rajendraj Rajendra Joshi (Inactive) made changes -
            Status Local Testing [ 10200 ] Reopen in Local [ 10018 ]
            rajendraj Rajendra Joshi (Inactive) made changes -
            Assignee Rajendra Joshi [ rajendraj ] Avnish Yadav [ avnish.yadav ]
            rajendraj Rajendra Joshi (Inactive) made changes -
            Time Spent 11.5h [ 41400 ] 12.5h [ 45000 ]
            Worklog Id 26485 [ 26485 ]
            rajendraj Rajendra Joshi (Inactive) made changes -
            Attachment LB-3.png [ 40381 ]
            Attachment LB-4.png [ 40382 ]
            rajendraj Rajendra Joshi (Inactive) made changes -
            Time Spent 12.5h [ 45000 ] 13h [ 46800 ]
            Worklog Id 26547 [ 26547 ]
            rajendraj Rajendra Joshi (Inactive) made changes -
            Worklog Id 26547 [ 26547 ]
            rajendraj Rajendra Joshi (Inactive) logged work - 23/Feb/17 05:19 AM
            • Time Spent:
              1h
               
              <No comment>
            rajendraj Rajendra Joshi (Inactive) logged work - 23/Feb/17 07:13 AM - edited
            • Time Spent:
              0.5h
               

              Verified with existing employee.

            avnish.yadav Avnish Yadav (Inactive) logged work - 24/Feb/17 06:15 PM
            • Time Spent:
              4h
               
              <No comment>
            avnish.yadav Avnish Yadav (Inactive) logged work - 27/Feb/17 06:18 PM - edited
            • Time Spent:
              4h
               
              <No comment>
            avnish.yadav Avnish Yadav (Inactive) made changes -
            Time Spent 13h [ 46800 ] 15h [ 54000 ]
            Worklog Id 28248 [ 28248 ]
            avnish.yadav Avnish Yadav (Inactive) made changes -
            Time Spent 15h [ 54000 ] 17h [ 61200 ]
            Worklog Id 28250 [ 28250 ]
            avnish.yadav Avnish Yadav (Inactive) made changes -
            Time Spent 17h [ 61200 ] 21h [ 75600 ]
            Worklog Id 28270 [ 28270 ]
            avnish.yadav Avnish Yadav (Inactive) made changes -
            Time Spent 21h [ 75600 ] 25h [ 90000 ]
            Worklog Id 28276 [ 28276 ]
            avnish.yadav Avnish Yadav (Inactive) made changes -
            Worklog Id 28276 [ 28276 ]
            avnish.yadav Avnish Yadav (Inactive) made changes -
            Item State Parent values: LB QA(10201)Level 1 values: Re-open(10212) Parent values: Development(10200)Level 1 values: Ready for Review(10208)
            avnish.yadav Avnish Yadav (Inactive) made changes -
            Status Reopen in Local [ 10018 ] In Development [ 10007 ]
            avnish.yadav Avnish Yadav (Inactive) made changes -
            Dev Due Date 07/Mar/2017
            khandu.kshirsagar Khandu Kshirsagar (Inactive) made changes -
            Item State Parent values: Development(10200)Level 1 values: Ready for Review(10208) Parent values: LB QA(10201)Level 1 values: LB Deployed(11600)
            avnish.yadav Avnish Yadav (Inactive) made changes -
            Assignee Avnish Yadav [ avnish.yadav ] Hrishikesh Deshpande [ hrishikesh.deshpande ]
            rakeshr Rakesh Roy (Inactive) made changes -
            Status In Development [ 10007 ] Local Testing [ 10200 ]
            hrishikesh.deshpande Hrishikesh Deshpande (Inactive) made changes -
            Assignee Hrishikesh Deshpande [ hrishikesh.deshpande ] Rajendra Joshi [ rajendraj ]
            Hide
            rajendraj Rajendra Joshi (Inactive) added a comment -

            Verified on LB using company Five Guys. Above issue are resolved now.

            Show
            rajendraj Rajendra Joshi (Inactive) added a comment - Verified on LB using company Five Guys. Above issue are resolved now.
            rajendraj Rajendra Joshi (Inactive) made changes -
            Time Spent 25h [ 90000 ] 26.25h [ 94500 ]
            Worklog Id 33116 [ 33116 ]
            rajendraj Rajendra Joshi (Inactive) made changes -
            Item State Parent values: LB QA(10201)Level 1 values: LB Deployed(11600) Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213)
            rajendraj Rajendra Joshi (Inactive) logged work - 24/Mar/17 06:57 AM
            • Time Spent:
              1.25h
               
              <No comment>
            khandu.kshirsagar Khandu Kshirsagar (Inactive) made changes -
            Item State Parent values: LB QA(10201)Level 1 values: Ready for Stage(10213) Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602)
            Hide
            rajendraj Rajendra Joshi (Inactive) added a comment -

            Verified on stage using restored company five guys for hspl. Above issue is fixed now.

            Show
            rajendraj Rajendra Joshi (Inactive) added a comment - Verified on stage using restored company five guys for hspl. Above issue is fixed now.
            rajendraj Rajendra Joshi (Inactive) made changes -
            Time Spent 26.25h [ 94500 ] 28.25h [ 101700 ]
            Worklog Id 34240 [ 34240 ]
            rajendraj Rajendra Joshi (Inactive) made changes -
            Status Local Testing [ 10200 ] Stage Testing [ 10201 ]
            rajendraj Rajendra Joshi (Inactive) made changes -
            Item State Parent values: Stage QA(10202)Level 1 values: Stage Deployed(11602) Parent values: Stage QA(10202)Level 1 values: Ready for Production(10217)
            rajendraj Rajendra Joshi (Inactive) logged work - 30/Mar/17 06:42 AM
            • Time Spent:
              2h
               
              <No comment>
            ashwin.wankhede Ashwin Wankhede (Inactive) made changes -
            Item State Parent values: Stage QA(10202)Level 1 values: Ready for Production(10217) Parent values: Production QA(10203)Level 1 values: Production Deployed(10221)
            rakeshr Rakesh Roy (Inactive) made changes -
            Status Stage Testing [ 10201 ] Production Testing [ 10202 ]
            Hide
            rajendraj Rajendra Joshi (Inactive) added a comment -

            Verified on Production using company Five guys for hspl. Above issue is fixed now.

            Show
            rajendraj Rajendra Joshi (Inactive) added a comment - Verified on Production using company Five guys for hspl. Above issue is fixed now.
            rajendraj Rajendra Joshi (Inactive) logged work - 03/Apr/17 12:53 PM
            • Time Spent:
              1.25h
               
              <No comment>
            rajendraj Rajendra Joshi (Inactive) made changes -
            Time Spent 28.25h [ 101700 ] 29.5h [ 106200 ]
            Worklog Id 35772 [ 35772 ]
            rajendraj Rajendra Joshi (Inactive) made changes -
            Resolution Unresolved [ 10200 ] Fixed [ 1 ]
            Status Production Testing [ 10202 ] Production Complete [ 10028 ]
            rajendraj Rajendra Joshi (Inactive) made changes -
            Item State Parent values: Production QA(10203)Level 1 values: Production Deployed(10221) Parent values: Production Complete(10222)Level 1 values: Closed(10223)
            rajendraj Rajendra Joshi (Inactive) made changes -
            Status Production Complete [ 10028 ] Closed [ 6 ]
            rakeshr Rakesh Roy (Inactive) made changes -
            Bug Severity Medium [ 16702 ]
            Dev Due Date 07/Mar/2017 07/Mar/2017
            Production Due Date 21/Feb/2017 21/Feb/2017
            Stage Due Date 20/Feb/17 [ 2017-02-20 ] 20/Feb/17 [ 2017-02-20 ]
            satyap Satya made changes -
            Environment_New Production [ 18442 ]
            Prashant.samal Prashant Samal (Inactive) made changes -
            Component/s ACA [ 10004 ]
            Component/s Exchange [ 10003 ]
            Transition Time In Source Status Execution Times
            Avnish Yadav (Inactive) made transition -
            Open In Development
            16h 19m 1
            Rajendra Joshi (Inactive) made transition -
            Stage Testing Reopened in Stage
            3s 1
            Avnish Yadav (Inactive) made transition -
            Reopened in Stage In Development
            57m 48s 1
            Rajendra Joshi (Inactive) made transition -
            In LB Testing Reopen in Local
            22h 52m 1
            Avnish Yadav (Inactive) made transition -
            Reopen in Local In Development
            11d 23h 49m 1
            Rakesh Roy (Inactive) made transition -
            In Development In LB Testing
            6d 11h 56m 3
            Rajendra Joshi (Inactive) made transition -
            In LB Testing Stage Testing
            22d 3h 58m 2
            Rakesh Roy (Inactive) made transition -
            Stage Testing In Production Testing
            5d 4h 57m 1
            Rajendra Joshi (Inactive) made transition -
            In Production Testing Production Complete
            1h 12m 1
            Rajendra Joshi (Inactive) made transition -
            Production Complete Closed
            18s 1

              People

              Assignee:
              rajendraj Rajendra Joshi (Inactive)
              Reporter:
              jjsassy99 Jennifer Johnson (Inactive)
              Account Executive:
              Jennifer Johnson (Inactive)
              Developer:
              Avnish Yadav (Inactive)
              QA:
              Rajendra Joshi (Inactive)
              Votes:
              0 Vote for this issue
              Watchers:
              6 Start watching this issue

                Dates

                Created:
                Updated:
                Resolved:
                Dev Due Date:
                Pre-Prod Due Date:
                Production Due Date:

                  Time Tracking

                  Estimated:
                  Original Estimate - 3h Original Estimate - 3h
                  3h
                  Remaining:
                  Remaining Estimate - 0h
                  0h
                  Logged:
                  Time Spent - 29.5h
                  29.5h