Uploaded image for project: 'WORKTERRA'
  1. WORKTERRA
  2. WT-10635

TIBCO & Other BCC Groups - Issues with plans with ER contribution

    Details

    • Type: Bug
    • Status: Closed
    • Priority: High
    • Resolution: Unresolved
    • Affects Version/s: None
    • Fix Version/s: None
    • Component/s: BenAdmin
    • Labels:
      None
    • Environment:
      Stage
    • Bug Severity:
      Medium
    • Module:
      BenAdmin - Enrollment
    • Reported by:
      Client
    • Company:
      TIBCO
    • Item State:
      Production Complete - Closed
    • Reported by Customer:
      BCC
    • Sprint:
      WT Sprint 35 - Bugs, WT Sprint 37 - Bugs

      Description

      test employee: Yearlyhsa Testing

      1. The ER contribution is not showing on the summary or confirmation statement when a change is made mid year


      2. The benefit is show that the benefit is both "waived" and "Enrolled"

      Kira Hamilton

        Attachments

          Issue Links

            Activity

            Transition Time In Source Status Execution Times
            Rohit Shete (Inactive) made transition -
            Open In Development
            10h 27m 1
            Satya made transition -
            In Development Rejected
            13d 2h 22m 1
            Satya made transition -
            Rejected Reopen
            9d 21h 41m 1
            Satya made transition -
            Reopen In Development
            13s 1
            Satya made transition -
            In LB Testing Reopen in Local
            5s 1
            Satya made transition -
            Reopen in Local In Development
            3s 1
            Rashmita Dudhe (Inactive) made transition -
            In Development In LB Testing
            5d 7h 44m 2
            Rashmita Dudhe (Inactive) made transition -
            In LB Testing Stage Testing
            1d 20h 35m 1
            Rashmita Dudhe (Inactive) made transition -
            Stage Testing In Production Testing
            3d 1h 1
            Rashmita Dudhe (Inactive) made transition -
            In Production Testing Production Complete
            25s 1
            Debbie Kulling made transition -
            Production Complete Closed
            162d 6h 29m 1

              People

              Assignee:
              dkulling Debbie Kulling
              Reporter:
              dkulling Debbie Kulling
              Account Executive:
              Debbie Kulling
              Developer:
              Rohit Shete (Inactive)
              Votes:
              0 Vote for this issue
              Watchers:
              6 Start watching this issue

                Dates

                Created:
                Updated:
                Dev Due Date:
                Pre-Prod Due Date:
                Production Due Date:
                Code Review Date:

                  Time Tracking

                  Estimated:
                  Original Estimate - 8h Original Estimate - 8h
                  8h
                  Remaining:
                  Remaining Estimate - 0h
                  0h
                  Logged:
                  Time Spent - 40h